PIPE,2IN,SCH160,P11,SMLS,6M LG
Material 4100028241 · PIPE · Plant 1000
AReduceNon-moving
- Material
- 4100028241
- Category
- PIPE
- Base unit
- LG
- MRP type
- Stock Item
- Criticality
- A (4 of 7 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 29 d · P80 51 d
- Unit price
- Rp 1.7M (est.)
Recommendation
- 1.Forecast 0.5 LG/year: 0.5 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~29 days; expected demand during lead time 0.0.
- 3.A 98.8% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 3.
- 4.Stock 14 exceeds the level to keep (3) by 11.
- 5.Installed on 7 FuncLoc(s), 4 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
14 / 0
no open PO
Today Min / Max
3 / 8
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
3
order qty 3
Service level
98.8%
stockout risk now 0%
Unit price
Rp 1.7M
Category + unit estimate
ML early warning: 18% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 42.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.
Installed on 7 functional locations
4 with criticality A/B · 40 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_HE-234C REFLUX EXCHANGER | A | 3 | 1 | 0.22 |
| PX_HE-118B C4 PRODUCT CONDENSER | A | 3 | 0 | 0.22 |
| PX_2-DS-23750-A41A-T PIPE-2 FROM PP-1384B TO HE-1975 | B | 12 | 0 | 0.01 |
| PX_HE-1562B SEAL OIL REBOILER | B | 12 | 0 | 0.22 |
| PX_16-FG-21944-B23A-T PIPE->16 FROM PP-280A TO PP-448 | C | 1 | 0 | 0.01 |
| PX_3-FG-15752-A21A-T PIPE-3 FROM KC-511C TO VD-422 | C | 3 | 0 | 0.01 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 6 | 8 | 3.02 |
Lead time and procurement
Lead time 29 ± 18 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 14 Sept 2026 | Medium | PX_BF-101 | Replace lamp as per PM finding |
| 16 Aug 2026 | Medium | PX_BF-101 | Install scaffolding at BF-101 |
| 22 Jun 2026 | Low | PX_BF-101 | Thermograph wall BF-101 |
| 06 Jun 2026 | Emergency | PX_BF-101 | Decoking follow up BF-101 |
| 27 Nov 2025 | Medium | PX_BF-101 | Peep door broken BF-101 |
| 15 Oct 2025 | Medium | PX_BF-101 | Install scaffolding at BF-101 |
| 13 Aug 2025 | Emergency | PX_BF-101 | Leak from packing |
| 02 Jun 2025 | Low | PX_BF-101 | Install cover plate BF-101 |
| 14 May 2025 | Medium | PX_HE-234C | PSM25/Leak from packing |
Recent goods issues
Never issued in the 17-month history.