PIPE,10IN,STD,SS316,SMLS,6M LG
Material 4100028249 · PIPE · Plant 1000
AReduceNon-moving
- Material
- 4100028249
- Category
- PIPE
- Base unit
- LG
- MRP type
- Stock Item
- Criticality
- A (2 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 29 d · P80 51 d
- Unit price
- Rp 1.7M (est.)
Recommendation
- 1.Forecast 2.5 LG/year: 2.5 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~29 days; expected demand during lead time 0.2.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
- 4.Stock 12 exceeds the level to keep (6) by 6.
- 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
12 / 0
no open PO
Today Min / Max
10 / 23
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
99.8%
stockout risk now 0%
Unit price
Rp 1.7M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 14 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 234.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.
Installed on 3 functional locations
2 with criticality A/B · 10 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-104 CRACKING FURNACE BF-104 | A | 6 | 28 | 11.58 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 1 | 23 | 9.01 |
| PX_1-CW-25324-A21A-T PIPE-1 FROM PP-1536B TO HE-1788D | C | 3 | 0 | 0.01 |
Lead time and procurement
Lead time 29 ± 18 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 16 Sept 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
| 13 Sept 2026 | Low | PX_BF-104 | Install cover plate for MCP cracking |
| 10 Sept 2026 | Medium | PX_BF-111 | Peep door broken BF-111 |
| 04 Sept 2026 | Medium | PX_BF-104 | Replace burner tip BF-104 |
| 01 Sept 2026 | Medium | PX_BF-104 | Install scaffolding at BF-104 |
| 29 Aug 2026 | High | PX_BF-104 | Leak from packing |
| 08 Aug 2026 | Low | PX_BF-104 | [MSI-B-26-MZB-191] Permanent repair |
| 04 Aug 2026 | Medium | PX_BF-104 | Thermograph wall BF-104 |
Recent goods issues
Never issued in the 17-month history.