PIPE,3/4IN,SCH80,CS,SMLS,6M LG
Material 4100028820 · PIPE · Plant 1000
AReduceSlow-moving
- Material
- 4100028820
- Category
- PIPE
- Base unit
- LG
- MRP type
- Stock Item
- Criticality
- A (3 of 4 FuncLocs A/B)
- Supplier
- SURYA INSTRUMEN MAKMUR PT
- Lead time
- 28 d · P80 51 d
- Unit price
- Rp 1.3M
Recommendation
- 1.Forecast 7.5 LG/year: 7.5 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~28 days; expected demand during lead time 0.6.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 14.
- 4.Stock 128 exceeds the level to keep (14) by 114.
- 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Single source
On hand / on order
128 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
14
order qty 8
Service level
100.0%
stockout risk now 0%
Unit price
Rp 1.3M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 271 days ago, 6 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.
Installed on 4 functional locations
3 with criticality A/B · 13 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-109 CRACKING FURNACE BF-109 | A | 1 | 29 | 11.58 |
| PX_HE-708A SLOP OIL COOLER | A | 3 | 1 | 0.22 |
| PX_HE-694C LEAN AMINE CONDENSER | B | 6 | 2 | 0.65 |
| PX_2-MS-13283-A51A-T PIPE-2 FROM PP-1574B TO VD-843C | C | 3 | 1 | 0.01 |
Lead time and procurement
Lead time 28 ± 18 days (PO history + category, 1 PO lines) · on-time 34%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 20 Mar 2026 | PR03 Regular replenishment | 2 | Rp 1.3M | 15 Apr 2026 | 26 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 20 Sept 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
| 13 Sept 2026 | Medium | PX_BF-109 | Install scaffolding at BF-109 |
| 03 Sept 2026 | Low | PX_BF-109 | Install scaffolding at BF-109 |
| 02 Sept 2026 | Low | PX_BF-109 | Install cover plate for MCP cracking |
| 16 Aug 2026 | Medium | PX_BF-109 | Install cover plate BF-109 |
| 13 Jul 2026 | Medium | PX_BF-109 | Cleaning burner BF-109 |
| 09 Jul 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
| 09 Jul 2026 | Low | PX_BF-109 | Leak from packing |
| 01 Jul 2026 | Emergency | PX_BF-109 | [MSI-B-26-YDN-280/M] Replace line |
| 23 Jun 2026 | High | PX_BF-109 | Cleaning burner BF-109 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 03 Jan 2026 | 2 | 201000019978 | Corrective |