ELBOW,90DEG,10IN,SCH80,A234WPB,SW

Material 4100029835 · ELBOW · Plant 1000

CMonitorHealthy
Material
4100029835
Category
ELBOW
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 3 FuncLocs A/B)
Supplier
NUSA ELEKTRIK SENTOSA PT
Lead time
21 d · P80 29 d
Unit price
Rp 147,573

Recommendation

  • 1.Forecast 35 EA/year: 35 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~21 days; expected demand during lead time 2.0.
  • 3.A 99.3% service level gives the lowest holding + downtime-risk cost: reorder at 11, order up to 47.
  • 4.ML early warning: 65% probability of demand in the next 90 days.
ML early warningLast turnaround used 4Single sourceAbnormal consumption
On hand / on order
43 / 0
no open PO
Today Min / Max
11 / 32
static parameters in BoM
Rec. Min (reorder point)
11
safety stock 9
Rec. Max
47
order qty 36
Service level
99.3%
stockout risk now 0%
Unit price
Rp 147,573
PO history
ML early warning: 65% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 103 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (22 units) excluded from the baseline.

Demand pattern Lumpy · 16 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 41.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~12 days.

Installed on 3 functional locations

0 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_20-MS-8358-A22A-HS
PIPE->16 FROM PP-583B TO VD-1859
C110.01
PX_12-IA-26555-D12A-T
PIPE-12 FROM KC-730 TO HE-286C
C100.01
PX_3-FG-17006-C11A-H
PIPE-3 FROM HE-152A TO PP-445
C400.01

Lead time and procurement

Lead time 21 ± 11 days (PO history, 11 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
04 Sept 2026PR06
Regular replenishment
23Rp 147,19523 Sept 202619 d
07 Aug 2026PR03
Regular replenishment
46Rp 154,03618 Aug 202611 d
05 Apr 2026PR05
Project / turnaround
21Rp 147,07009 May 202634 d
26 Mar 2026PR04
Regular (other)
13Rp 145,86920 Apr 202625 d
05 Jan 2026PR06
Regular replenishment
32Rp 145,10727 Jan 202622 d
19 Nov 2025PR06
Regular replenishment
37Rp 145,42725 Dec 202536 d
18 Nov 2025PR03
Regular replenishment
45Rp 147,57328 Nov 202510 d
16 Sept 2025PR03
Regular replenishment
26Rp 148,57327 Sept 202511 d
17 Jul 2025PR06
Regular replenishment
23Rp 149,40006 Aug 202520 d
24 Jun 2025PR03
Regular replenishment
15Rp 149,71002 Jul 20258 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
27 May 2025MediumPX_20-MS-8358-A22A-HSClean dummy leg 20-MS-8358-A22A-HS

Recent goods issues

Posting dateQtyOrderOrder type
20 Jun 20262209000027470Other maintenance
04 Feb 20267201000028594Corrective
19 Jan 20264201000023909Corrective
29 Dec 20256201000025505Corrective
14 Dec 20251204000014979Preventive
08 Nov 20254203000026396Turnaround
03 Nov 20251201000005391Corrective
31 Oct 20255201000036040Corrective
31 Oct 202510209000022917Other maintenance
14 Oct 20254201000007548Corrective
22 Sept 20254201000004313Corrective
19 Sept 20258201000010418Corrective
19 Sept 20252201000025947Corrective
03 Sept 202512201000026549Corrective
29 Aug 20258201000032106Corrective