ELBOW,90DEG,1/2IN,SCH40,A234WPB,BW
Material 4100029933 · ELBOW · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100029933
- Category
- ELBOW
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 24 d · P80 41 d
- Unit price
- Rp 219,925 (est.)
Recommendation
- 1.Forecast 8.0 EA/year: 8.0 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~24 days; expected demand during lead time 0.5.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 13.
- 4.On hand 3 + on order 0 is at or below the reorder point: order 10 now.
- 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
10 EA
Rp 2.2M · order by 01 Oct 2026
Expected arrival ≈ 24 days
Price estimatedLead time estimated
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
13
order qty 9
Service level
100.0%
stockout risk now 0%
Unit price
Rp 219,925
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 11 days ago, 20 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~12 days.
Installed on 3 functional locations
1 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-104 CRACKING FURNACE BF-104 | A | 3 | 28 | 11.58 |
| PX_6-P-15791-B21A-HS PIPE-6 FROM CL-1871 TO PP-818B | C | 1 | 0 | 0.01 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 1 | 41 | 14.58 |
Lead time and procurement
Lead time 24 ± 13 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 16 Sept 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
| 15 Sept 2026 | Medium | PX_BF-110 | Decoking follow up BF-110 |
| 13 Sept 2026 | Low | PX_BF-104 | Install cover plate for MCP cracking |
| 11 Sept 2026 | Medium | PX_BF-110 | Leak from packing |
| 04 Sept 2026 | Medium | PX_BF-104 | Replace burner tip BF-104 |
| 03 Sept 2026 | Low | PX_BF-110 | Hot spot at convection BF-110 |
| 03 Sept 2026 | Medium | PX_BF-110 | Thermograph wall BF-110 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 20 Sept 2026 | 1 | 201000022167 | Corrective |