ELBOW,45DEG,12IN,3000#,SS316,SW
Material 4100029976 · ELBOW · Plant 1000
AReorderCriticalStockout
- Material
- 4100029976
- Category
- ELBOW
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 5 FuncLocs A/B)
- Supplier
- SAMUDRA SEJAHTERA INTERNASIONAL PT
- Lead time
- 24 d · P80 41 d
- Unit price
- Rp 46,480
Recommendation
- 1.Forecast 16 EA/year: 16 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~24 days; expected demand during lead time 1.0.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 22.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 22 now.
- 5.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
22 EA
Rp 1.0M · order by 01 Oct 2026
Expected arrival ≈ 24 days
Single source
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 5
Rec. Max
22
order qty 16
Service level
99.9%
stockout risk now 50%
Unit price
Rp 46,480
PO history
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 93 days ago, 24 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~12 days.
Installed on 5 functional locations
4 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-112 CRACKING FURNACE BF-112 | A | 1 | 73 | 27.01 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 1 | 23 | 9.01 |
| PX_3/4-FG-3567-A11A-T PIPE-3/4 FROM PP-1011D TO VD-462 | A | 1 | 0 | 0.01 |
| PX_12-BF-24554-A11A-HS PIPE-12 FROM HE-530D TO PP-688 | B | 1 | 0 | 0.01 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 1 | 23 | 9.44 |
Lead time and procurement
Lead time 24 ± 13 days (PO history + category, 1 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 23 Nov 2025 | PR03 Regular replenishment | 2 | Rp 46,480 | 17 Dec 2025 | 24 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
| 10 Sept 2026 | Medium | PX_BF-108 | [MSI-B-26-JJB-193] Permanent repair |
| 08 Sept 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 07 Sept 2026 | Medium | PX_BF-108 | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Jun 2026 | 2 | 201000031423 | Corrective |
| 06 Aug 2025 | 1 | 201000019352 | Corrective |