ELBOW,45DEG,10IN,SCH40,A234WPB,BW

Material 4100030406 · ELBOW · Plant 1000

CReduceExcess
Material
4100030406
Category
ELBOW
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 2 FuncLocs A/B)
Supplier
SINAR TEKNIK INTERNASIONAL PT
Lead time
18 d · P80 41 d
Unit price
Rp 31,603

Recommendation

  • 1.Forecast 1.6 EA/year: 1.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~18 days; expected demand during lead time 0.1.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
  • 4.Stock 45 exceeds the level to keep (6) by 39.
Single source
On hand / on order
45 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
100.0%
stockout risk now 0%
Unit price
Rp 31,603
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 88 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~12 days.

Installed on 2 functional locations

0 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_3/4-DS-24384-B22A-T
PIPE-3/4 FROM PP-1280B TO HE-234C
C120.44
PX_1-LS-3481-C11A-T
PIPE-1 FROM PP-1524A TO CL-682
C100.01

Lead time and procurement

Lead time 18 ± 13 days (PO history + category, 2 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
16 Sept 2026PR03
Regular replenishment
1Rp 31,22925 Sept 20269 d
14 Aug 2025PR06
Regular replenishment
2Rp 31,97625 Aug 202511 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
02 Jun 2026LowPX_3/4-DS-24384-B22A-TLeak from packing
27 May 2025MediumPX_3/4-DS-24384-B22A-T[MSI-B-25-MTE-201/M] Replace line

Recent goods issues

Posting dateQtyOrderOrder type
05 Jul 20263201000038942Corrective