TEE,8IN,SCH40,A105,SW
Material 4100031136 · TEE · Plant 1000
AReduceExcess
- Material
- 4100031136
- Category
- TEE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 21 FuncLocs A/B)
- Supplier
- KARYA UTAMA GLOBAL PT
- Lead time
- 31 d · P80 40 d
- Unit price
- Rp 856,636
Recommendation
- 1.Forecast 408 EA/year: 408 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~31 days; expected demand during lead time 34.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 101, order up to 186.
- 4.Stock 284 exceeds the level to keep (186) by 98.
- 5.Installed on 21 FuncLoc(s), 4 of them criticality A/B.
- 6.ML early warning: 100% probability of demand in the next 90 days.
ML early warningLast turnaround used 130Single sourceAbnormal consumptionOpen PO
On hand / on order
284 / 131
next delivery 06 Oct 2026
Today Min / Max
70 / 137
static parameters in BoM
Rec. Min (reorder point)
101
safety stock 67
Rec. Max
186
order qty 85
Service level
99.9%
stockout risk now 0%
Unit price
Rp 856,636
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 46 issue days in the last 180 days, last issue 2 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 19 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (172 units) excluded from the baseline.
Demand pattern Smooth · 160 issue days · 22 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 27.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~12 days.
Installed on 21 functional locations
4 with criticality A/B · 27 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_3/4-DS-20719-A21A-T PIPE-3/4 FROM VD-123A TO HE-1483A | A | 1 | 1 | 0.01 |
| PX_16-DS-24185-C11A-T PIPE->16 FROM VD-433 TO VD-1771 | B | 1 | 1 | 0.01 |
| PX_1-CW-17409-B23A-T PIPE-1 FROM HE-1561D TO HE-686C | B | 1 | 0 | 0.01 |
| PX_2-DS-12644-D12A-HS PIPE-2 FROM VD-1609A TO PP-700 | B | 1 | 0 | 0.01 |
| PX_1-CW-4270-A51A-T PIPE-1 FROM KC-369B TO VD-1906 | C | 3 | 2 | 0.44 |
| PX_1-HS-24003-A41A-HS PIPE-1 FROM VD-1417C TO VD-269 | C | 2 | 2 | 0.44 |
| PX_2-BF-27803-A21A PIPE-2 FROM VD-450 TO HE-589D | C | 1 | 1 | 0.44 |
| PX_1-1/2-HS-14597-A11A-T PIPE-1-1/2 FROM HE-1363A TO HE-1217C | C | 1 | 0 | 0.01 |
| PX_1-DS-24049-B23A-T PIPE-1 FROM PP-1864A TO PP-455D | C | 1 | 0 | 0.01 |
| PX_1-FG-3358-D12A-C PIPE-1 FROM KC-223 TO PP-128A | C | 1 | 0 | 0.01 |
| PX_1-P-12689-B22A PIPE-1 FROM PP-315A TO VD-664B | C | 1 | 0 | 0.01 |
| PX_2-BF-17622-A41A-HS PIPE-2 FROM HE-1423C TO PP-517A | C | 1 | 0 | 0.01 |
Lead time and procurement
Lead time 31 ± 15 days (PO history, 49 PO lines) · on-time 45%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 03 Sept 2026 | PR03 Regular replenishment | 131 | Rp 876,805 | 06 Oct 2026 open | 33 d |
| 22 Aug 2026 | PR03 Regular replenishment | 312 | Rp 841,395 | 30 Sept 2026 | 39 d |
| 15 Aug 2026 | PR03 Regular replenishment | 346 | Rp 884,567 | 17 Sept 2026 | 33 d |
| 10 Aug 2026 | PR03 Regular replenishment | 448 | Rp 863,276 | 05 Sept 2026 | 26 d |
| 19 Jul 2026 | PR03 Regular replenishment | 325 | Rp 854,836 | 17 Aug 2026 | 29 d |
| 16 Jul 2026 | PR06 Regular replenishment | 139 | Rp 874,996 | 09 Sept 2026 | 55 d |
| 15 Jul 2026 | PR03 Regular replenishment | 332 | Rp 824,793 | 25 Aug 2026 | 41 d |
| 10 Jul 2026 | PR01 Import / long-lead | 278 | Rp 879,273 | 16 Aug 2026 | 37 d |
| 27 Jun 2026 | PR03 Regular replenishment | 413 | Rp 848,225 | 11 Jul 2026 | 14 d |
| 23 Jun 2026 | PR04 Regular (other) | 201 | Rp 877,173 | 18 Aug 2026 | 56 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 25 Aug 2026 | Medium | PX_1-CW-4270-A51A-T | Reinject compound online clamp sealing |
| 10 Jun 2026 | Medium | PX_1-HS-24003-A41A-HS | Thickness measurement 1-HS-24003-A41A-HS |
| 03 Jun 2025 | Medium | PX_2-BF-27803-A21A | Leak from packing |
| 30 May 2025 | Medium | PX_1-HS-24003-A41A-HS | Replace pipe 1-HS-24003-A41A-HS |
| 14 May 2025 | Medium | PX_1-CW-4270-A51A-T | Clean dummy leg 1-CW-4270-A51A-T |
| 12 May 2025 | Medium | PX_3/4-DS-20719-A21A-T | Leak from packing |
| 07 May 2025 | Medium | PX_16-DS-24185-C11A-T | Reinject compound online clamp sealing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 29 Sept 2026 | 2 | 204000037489 | Preventive |
| 26 Sept 2026 | 4 | 209000029477 | Other maintenance |
| 22 Sept 2026 | 1 | 201000039118 | Corrective |
| 21 Sept 2026 | 1 | 201000023715 | Corrective |
| 13 Sept 2026 | 2 | 201000031756 | Corrective |
| 10 Sept 2026 | 2 | 201000016998 | Corrective |
| 06 Sept 2026 | 4 | 203000008243 | Turnaround |
| 01 Sept 2026 | 3 | 201000003615 | Corrective |
| 31 Aug 2026 | 4 | 204000022675 | Preventive |
| 29 Aug 2026 | 3 | 201000004962 | Corrective |
| 28 Aug 2026 | 2 | 201000016249 | Corrective |
| 27 Aug 2026 | 5 | 201000016249 | Corrective |
| 24 Aug 2026 | 3 | 201000000994 | Corrective |
| 23 Aug 2026 | 4 | 201000000994 | Corrective |
| 23 Aug 2026 | 1 | 201000025104 | Corrective |