TEE,12IN,SCH80,A234WPB,BW

Material 4100031227 · TEE · Plant 1000

BMonitorHealthy
Material
4100031227
Category
TEE
Base unit
EA
MRP type
Stock Item
Criticality
B (1 of 6 FuncLocs A/B)
Supplier
SAMUDRA SEJAHTERA INTERNASIONAL PT
Lead time
55 d · P80 82 d
Unit price
Rp 92,866

Recommendation

  • 1.Forecast 71 EA/year: 71 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~55 days; expected demand during lead time 11.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 35, order up to 107.
  • 4.Installed on 6 FuncLoc(s), 1 of them criticality A/B.
  • 5.ML early warning: 99% probability of demand in the next 90 days.
ML early warningLast turnaround used 8Single sourceAbnormal consumptionOpen PO
On hand / on order
45 / 35
next delivery 06 Nov 2026
Today Min / Max
38 / 100
static parameters in BoM
Rec. Min (reorder point)
35
safety stock 25
Rec. Max
107
order qty 72
Service level
99.9%
stockout risk now 0%
Unit price
Rp 92,866
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 8 issue days in the last 180 days, last issue 22 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (16 units) excluded from the baseline.

Demand pattern Smooth · 31 issue days · 3 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~12 days.

Installed on 6 functional locations

1 with criticality A/B · 8 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_2-P-2392-A22A
PIPE-2 FROM PP-752B TO PP-497A
B100.01
PX_3-FG-4642-A22A-H
PIPE-3 FROM PP-563 TO VD-468
C310.01
PX_1-1/2-DS-23086-A22A-C
PIPE-1-1/2 FROM PP-301C TO VD-1110B
C100.01
PX_1-QO-7942-A11A-HS
PIPE-1 FROM VD-1447 TO PP-682A
C100.01
PX_2-IA-23649-A21A-T
PIPE-2 FROM PP-210A TO PP-1834B
C100.01
PX_3/4-CW-17731-B22A-C
PIPE-3/4 FROM PP-1905A TO HE-395B
C100.01

Lead time and procurement

Lead time 55 ± 37 days (PO history, 10 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
22 Sept 2026PR03
Regular replenishment
35Rp 92,97906 Nov 2026
open
45 d
29 Jul 2026PR06
Regular replenishment
27Rp 98,89426 Sept 202659 d
26 Jun 2026PR03
Regular replenishment
34Rp 92,75227 Jul 202631 d
13 Jun 2026PR03
Regular replenishment
33Rp 91,67520 Jul 202637 d
03 Apr 2026PR01
Import / long-lead
28Rp 96,44419 Jun 202677 d
09 Dec 2025PR03
Regular replenishment
48Rp 91,51806 Jan 202628 d
15 Oct 2025PR03
Regular replenishment
57Rp 96,65926 Nov 202542 d
02 Sept 2025PR06
Regular replenishment
19Rp 94,45910 Oct 202538 d
07 Aug 2025PR01
Import / long-lead
52Rp 92,10317 Jan 2026163 d
07 Jul 2025PR04
Regular (other)
35Rp 92,64116 Oct 2025101 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 May 2025MediumPX_3-FG-4642-A22A-HInstall scaffolding at 3-FG-4642-A22A-H

Recent goods issues

Posting dateQtyOrderOrder type
09 Sept 20266204000028728Preventive
04 Sept 20264204000038666Preventive
03 Aug 20265201000035128Corrective
21 Jun 20264209000014083Other maintenance
11 Jun 20264201000023717Corrective
04 Jun 20262201000005500Corrective
28 Apr 20264201000019885Corrective
07 Apr 20262201000039783Corrective
28 Mar 20262201000031899Corrective
29 Jan 20262201000017678Corrective
24 Jan 20262201000039852Corrective
23 Jan 20261201000007323Corrective
23 Jan 20264201000007323Corrective
09 Jan 20263201000016973Corrective
06 Jan 20269201000016937Corrective