TEE,3IN,SCH80,A105,SW
Material 4100031340 · TEE · Plant 1000
BReduceExcess
- Material
- 4100031340
- Category
- TEE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- B (1 of 2 FuncLocs A/B)
- Supplier
- GUNUNG INDUSTRI PRATAMA PT
- Lead time
- 28 d · P80 35 d
- Unit price
- Rp 1.3M
Recommendation
- 1.Forecast 26 EA/year: 26 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~28 days; expected demand during lead time 2.0.
- 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 9, order up to 27.
- 4.Stock 565 exceeds the level to keep (27) by 538.
- 5.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
- 6.ML early warning: 60% probability of demand in the next 90 days.
ML early warningLast turnaround used 6Single sourceOpen PO
On hand / on order
565 / 15
next delivery 07 Oct 2026
Today Min / Max
104 / 254
static parameters in BoM
Rec. Min (reorder point)
9
safety stock 8
Rec. Max
27
order qty 18
Service level
99.5%
stockout risk now 0%
Unit price
Rp 1.3M
PO history
ML early warning: 60% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 15 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (26 units) excluded from the baseline.
Demand pattern Intermittent · 19 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 572.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~12 days.
Installed on 2 functional locations
1 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_1-1/2-IA-27583-B21A-C PIPE-1-1/2 FROM PP-1106A TO VD-1095A | B | 1 | 0 | 0.01 |
| PX_1-1/2-HS-18026-A41A-HS PIPE-1-1/2 FROM VD-939 TO KC-853D | C | 3 | 0 | 0.01 |
Lead time and procurement
Lead time 28 ± 19 days (PO history, 5 PO lines) · on-time 45%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 08 Sept 2026 | PR03 Regular replenishment | 15 | Rp 1.3M | 07 Oct 2026 open | 29 d |
| 24 May 2026 | PR03 Regular replenishment | 37 | Rp 1.3M | 03 Jun 2026 | 10 d |
| 23 Feb 2026 | PR06 Regular replenishment | 20 | Rp 1.3M | 09 Mar 2026 | 14 d |
| 15 Feb 2026 | PR01 Import / long-lead | 32 | Rp 1.3M | 16 Apr 2026 | 60 d |
| 18 Sept 2025 | PR03 Regular replenishment | 32 | Rp 1.3M | 08 Oct 2025 | 20 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 16 Sept 2026 | 2 | 201000015263 | Corrective |
| 02 Sept 2026 | 20 | 203000008243 | Turnaround |
| 08 May 2026 | 4 | 201000013238 | Corrective |
| 02 Feb 2026 | 7 | 201000009533 | Corrective |
| 26 Jan 2026 | 2 | 201000030872 | Corrective |
| 16 Jan 2026 | 2 | 203000029956 | Turnaround |
| 01 Jan 2026 | 4 | 201000005842 | Corrective |
| 08 Dec 2025 | 3 | 201000019858 | Corrective |
| 25 Nov 2025 | 3 | 201000029876 | Corrective |
| 23 Nov 2025 | 4 | 201000017774 | Corrective |
| 11 Nov 2025 | 5 | 201000024602 | Corrective |
| 11 Nov 2025 | 4 | 203000030064 | Turnaround |
| 25 Oct 2025 | 1 | 201000010563 | Corrective |
| 16 Oct 2025 | 2 | 201000025573 | Corrective |
| 22 Sept 2025 | 2 | 201000005644 | Corrective |