Sparely
DU

TEE,3/4IN,SCH80,A234WPB,BW

Material 4100031630 · TEE · Plant 1000

CReorderHighStockout
Material
4100031630
Category
TEE
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 3 FuncLocs A/B)
Supplier
BUANA TEKNIK SENTOSA PT
Lead time
26 d · P80 51 d
Unit price
Rp 153,434

Recommendation

  • 1.Forecast 1.2 EA/year: 1.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~26 days; expected demand during lead time 0.1.
  • 3.A 96.6% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 3.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 3 now.
Proposed purchase requisition
3 EA
Rp 460,302 · order by 01 Oct 2026
Expected arrival ≈ 26 days
Single source
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
3
order qty 3
Service level
96.6%
stockout risk now 3%
Unit price
Rp 153,434
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 243 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~12 days.

Installed on 3 functional locations

0 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_1-1/2-LS-6362-A21A
PIPE-1-1/2 FROM VD-1513 TO PP-455D
C100.01
PX_16-HS-5180-D12A-H
PIPE->16 FROM HE-320A TO HE-1334
C100.01
PX_4-FG-13596-A22A-HS
PIPE-4 FROM HE-1982 TO CL-634
C100.01

Lead time and procurement

Lead time 26 ± 18 days (PO history + category, 1 PO lines) · on-time 29%

PR dateTypeQtyUnit priceDeliveryLead time
29 Jun 2026PR06
Regular replenishment
1Rp 153,43411 Jul 202612 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
31 Jan 20263201000005002Corrective
13 Jul 20252209000033701Other maintenance
Sparely