TEE,1/2IN,SCH40,A105,SW
Material 4100031731 · TEE · Plant 1000
CMonitorHealthy
- Material
- 4100031731
- Category
- TEE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- C (0 of 2 FuncLocs A/B)
- Supplier
- RAJAWALI INSTRUMEN INTERNASIONAL PT
- Lead time
- 29 d · P80 38 d
- Unit price
- Rp 654,792
Recommendation
- 1.Forecast 16 EA/year: 16 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~29 days; expected demand during lead time 1.3.
- 3.A 85.2% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 16.
Single source
On hand / on order
3 / 0
no open PO
Today Min / Max
2 / 6
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
16
order qty 16
Service level
85.2%
stockout risk now 15%
Unit price
Rp 654,792
PO history
ML early warning: 19% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 14 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 12.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~12 days.
Installed on 2 functional locations
0 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_1-1/2-IA-27265-A51A-C PIPE-1-1/2 FROM HE-819 TO CL-672 | C | 1 | 0 | 0.01 |
| PX_6-HS-18874-A22A-H PIPE-6 FROM PP-1729A TO HE-902 | C | 1 | 0 | 0.01 |
Lead time and procurement
Lead time 29 ± 20 days (PO history, 4 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 09 Apr 2026 | PR03 Regular replenishment | 7 | Rp 647,406 | 01 May 2026 | 22 d |
| 12 Dec 2025 | PR03 Regular replenishment | 10 | Rp 668,662 | 23 Dec 2025 | 11 d |
| 10 Aug 2025 | PR01 Import / long-lead | 6 | Rp 643,643 | 10 Oct 2025 | 61 d |
| 12 May 2025 | PR06 Regular replenishment | 11 | Rp 662,178 | 31 May 2025 | 19 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 17 Sept 2026 | 1 | 201000017824 | Corrective |
| 17 Sept 2026 | 8 | 201000017824 | Corrective |
| 23 Apr 2026 | 9 | 204000033648 | Preventive |
| 22 Apr 2026 | 2 | 204000033648 | Preventive |
| 22 Apr 2026 | 4 | 204000033648 | Preventive |