FLANGE,SO,8IN,150#,SS316,RF

Material 4100032890 · FLANGE · Plant 1000

AReduceExcess
Material
4100032890
Category
FLANGE
Base unit
EA
MRP type
Stock Item
Criticality
A (7 of 12 FuncLocs A/B)
Supplier
SINAR TEKNIK INTERNASIONAL PT
Lead time
68 d · P80 69 d
Unit price
Rp 613,178

Recommendation

  • 1.Forecast 69 EA/year: 69 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~68 days; expected demand during lead time 13.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 58, order up to 100.
  • 4.Stock 601 exceeds the level to keep (100) by 501.
  • 5.Installed on 12 FuncLoc(s), 7 of them criticality A/B.
  • 6.ML early warning: 99% probability of demand in the next 90 days.
ML early warningLast turnaround used 28Single sourceOpen PO
On hand / on order
601 / 66
next delivery 23 Oct 2026
Today Min / Max
13 / 35
static parameters in BoM
Rec. Min (reorder point)
58
safety stock 46
Rec. Max
100
order qty 42
Service level
99.9%
stockout risk now 0%
Unit price
Rp 613,178
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 8 issue days in the last 180 days, last issue 46 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (40 units) excluded from the baseline.

Demand pattern Erratic · 36 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 8.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~19 days.

Installed on 12 functional locations

7 with criticality A/B · 15 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_3/4-DS-9130-D12A-HS
PIPE-3/4 FROM PP-1280B TO VD-278A
A100.01
PX_HE-301B
FUEL OIL REBOILER
A200.22
PX_HE-706A
SEAL OIL TLE
B120.65
PX_HE-1086C
SEAL OIL PREHEATER
B310.65
PX_10-HS-10879-A11A-H
PIPE-10 FROM PP-1166B TO VD-148B
B100.01
PX_HE-144B
FUEL OIL CONDENSER
B100.22
PX_HE-463B
FUEL OIL PREHEATER
B100.22
PX_HE-1459D
SEAL OIL CONDENSER
C120.65
PX_HE-1008A
C3 RECYCLE CONDENSER
C100.22
PX_HE-1468A
INHIBITOR EXCHANGER
C100.22
PX_ROF-1048A
LP STEAM TO HE-1950
C100.00
PX_ROF-1907
RESTRICTION ORIFICE
C100.00

Lead time and procurement

Lead time 68 ± 63 days (PO history, 6 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
17 Sept 2026PR06
Regular replenishment
66Rp 595,20023 Oct 2026
open
36 d
27 Jun 2026PR06
Regular replenishment
57Rp 595,35726 Aug 202660 d
18 Feb 2026PR06
Regular replenishment
46Rp 635,36828 Apr 202669 d
07 Feb 2026PR03
Regular replenishment
53Rp 624,09601 Mar 202622 d
28 Sept 2025PR01
Import / long-lead
65Rp 623,54431 May 2026245 d
14 Jul 2025PR03
Regular replenishment
39Rp 602,81106 Sept 202554 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_HE-1459DHE-1459D fouling
14 Dec 2025MediumPX_HE-706AReplace lamp as per PM finding
25 Aug 2025MediumPX_HE-706AInstall scaffolding at HE-706A
02 Jun 2025MediumPX_HE-1086CReplace lamp as per PM finding
24 May 2025MediumPX_HE-1459DPSM25/Install scaffolding at HE-1459D

Recent goods issues

Posting dateQtyOrderOrder type
16 Aug 20264201000027971Corrective
04 Jul 20264201000008253Corrective
27 Jun 20264209000028044Other maintenance
17 Jun 20267201000013967Corrective
15 Jun 20261201000024527Corrective
31 May 20264201000003413Corrective
22 May 20268203000011209Turnaround
15 May 20262201000007315Corrective
11 May 20261201000031468Corrective
26 Feb 20261201000000733Corrective
08 Feb 20261204000016349Preventive
07 Feb 20267201000028862Corrective
25 Jan 20269201000030872Corrective
20 Jan 20261201000011893Corrective
12 Jan 20265201000026282Corrective