FLANGE,WN,12IN,300#,SS316,RF
Material 4100032965 · FLANGE · Plant 1000
AMaintainStockout
- Material
- 4100032965
- Category
- FLANGE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 10 FuncLocs A/B)
- Supplier
- MEGA TEKNOLOGI SENTOSA PT
- Lead time
- 46 d · P80 56 d
- Unit price
- Rp 1.1M
Recommendation
- 1.Forecast 69 EA/year: 69 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~46 days; expected demand during lead time 8.7.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 36, order up to 67.
- 4.Installed on 10 FuncLoc(s), 2 of them criticality A/B.
- 5.ML early warning: 95% probability of demand in the next 90 days.
ML early warningLast turnaround used 4Single sourceOpen PO
On hand / on order
0 / 53
next delivery 23 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
36
safety stock 28
Rec. Max
67
order qty 31
Service level
100.0%
stockout risk now 0%
Unit price
Rp 1.1M
PO history
ML early warning: 95% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 8 issue days in the last 180 days, last issue 36 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (40 units) excluded from the baseline.
Demand pattern Erratic · 22 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 5.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~19 days.
Installed on 10 functional locations
2 with criticality A/B · 10 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_HE-513D C4 PRODUCT CONDENSER | A | 1 | 0 | 0.22 |
| PX_HE-1810B CHARGE GAS REBOILER | B | 1 | 0 | 0.22 |
| PX_16-IA-21393-A22A PIPE->16 FROM PP-1363 TO VD-756B | C | 1 | 5 | 1.73 |
| PX_3-CW-5327-B22A-C PIPE-3 FROM VD-651B TO HE-1261C | C | 1 | 2 | 0.44 |
| PX_1-P-25691-D12A-H PIPE-1 FROM HE-237B TO HE-406A | C | 1 | 0 | 0.01 |
| PX_10-BF-15210-A22A-C PIPE-10 FROM PP-1205A TO HE-163A | C | 1 | 0 | 0.01 |
| PX_3/4-FG-27730-A51A-HS PIPE-3/4 FROM PP-958B TO PP-1393B | C | 1 | 0 | 0.01 |
| PX_4-LS-18269-B23A-H PIPE-4 FROM HE-182C TO HE-1975 | C | 1 | 0 | 0.01 |
| PX_6-LS-1466-A22A-H PIPE-6 FROM VD-1095A TO PP-143A | C | 1 | 0 | 0.01 |
| PX_ROF-443 MP STEAM TO PP-765B | C | 1 | 0 | 0.00 |
Lead time and procurement
Lead time 46 ± 22 days (PO history, 14 PO lines) · on-time 37%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 13 Aug 2026 | PR05 Project / turnaround | 53 | Rp 1.2M | 23 Nov 2026 open | 102 d |
| 01 Aug 2026 | PR06 Regular replenishment | 62 | Rp 1.2M | 27 Sept 2026 | 57 d |
| 24 May 2026 | PR03 Regular replenishment | 47 | Rp 1.2M | 29 Jun 2026 | 36 d |
| 20 May 2026 | PR03 Regular replenishment | 46 | Rp 1.2M | 04 Jul 2026 | 45 d |
| 03 Apr 2026 | PR03 Regular replenishment | 34 | Rp 1.1M | 23 Apr 2026 | 20 d |
| 03 Apr 2026 | PR06 Regular replenishment | 25 | Rp 1.1M | 27 May 2026 | 54 d |
| 02 Apr 2026 | PR06 Regular replenishment | 24 | Rp 1.1M | 28 Apr 2026 | 26 d |
| 19 Feb 2026 | PR03 Regular replenishment | 62 | Rp 1.1M | 24 Mar 2026 | 33 d |
| 30 Nov 2025 | PR03 Regular replenishment | 38 | Rp 1.1M | 28 Dec 2025 | 28 d |
| 03 Nov 2025 | PR03 Regular replenishment | 55 | Rp 1.2M | 29 Dec 2025 | 56 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 23 Aug 2026 | Medium | PX_16-IA-21393-A22A | [MSI-B-26-PHR-148] Permanent repair |
| 18 Aug 2026 | Medium | PX_16-IA-21393-A22A | Replace pipe 16-IA-21393-A22A |
| 27 Jul 2026 | Medium | PX_16-IA-21393-A22A | Reinject compound online clamp sealing |
| 25 Oct 2025 | Low | PX_16-IA-21393-A22A | Thickness measurement 16-IA-21393-A22A |
| 21 Sept 2025 | Low | PX_3-CW-5327-B22A-C | Thickness measurement 3-CW-5327-B22A-C |
| 09 May 2025 | Medium | PX_16-IA-21393-A22A | Leak at 16-IA-21393-A22A |
| 02 May 2025 | Medium | PX_3-CW-5327-B22A-C | Install scaffolding at 3-CW-5327-B22A-C |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 03 Sept 2026 | 22 | 203000008243 | Turnaround |
| 26 Aug 2026 | 6 | 201000028982 | Corrective |
| 06 Jul 2026 | 3 | 201000016715 | Corrective |
| 30 Jun 2026 | 5 | 201000016139 | Corrective |
| 19 Jun 2026 | 2 | 201000034999 | Corrective |
| 08 Jun 2026 | 2 | 201000002348 | Corrective |
| 24 May 2026 | 8 | 201000012062 | Corrective |
| 13 May 2026 | 6 | 201000024375 | Corrective |
| 29 Apr 2026 | 14 | 203000029810 | Turnaround |
| 10 Apr 2026 | 1 | 201000034612 | Corrective |
| 21 Mar 2026 | 3 | 201000019963 | Corrective |
| 04 Mar 2026 | 2 | 201000011654 | Corrective |
| 26 Jan 2026 | 6 | 201000027275 | Corrective |
| 28 Dec 2025 | 5 | 201000019016 | Corrective |
| 14 Dec 2025 | 3 | 201000013722 | Corrective |