FLANGE,BLIND,1-1/2IN,150#,A105,RF

Material 4100033000 · FLANGE · Plant 1000

AMonitorHealthy
Material
4100033000
Category
FLANGE
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 5 FuncLocs A/B)
Supplier
RAJAWALI INSTRUMEN INTERNASIONAL PT
Lead time
71 d · P80 87 d
Unit price
Rp 209,615

Recommendation

  • 1.Forecast 42 EA/year: 42 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~71 days; expected demand during lead time 8.2.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 27, order up to 70.
  • 4.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
  • 5.ML early warning: 97% probability of demand in the next 90 days.
ML early warningLast turnaround used 24Single sourceAbnormal consumptionOpen PO
On hand / on order
32 / 19
next delivery 16 Oct 2026
Today Min / Max
13 / 23
static parameters in BoM
Rec. Min (reorder point)
27
safety stock 19
Rec. Max
70
order qty 43
Service level
99.9%
stockout risk now 0%
Unit price
Rp 209,615
PO history
ML early warning: 97% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 87 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 5 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (44 units) excluded from the baseline.

Demand pattern Lumpy · 26 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 5.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~19 days.

Installed on 5 functional locations

2 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_8-CW-14050-A51A-T
PIPE-8 FROM PP-682A TO HE-1479B
A100.01
PX_HE-902
BFW PREHEATER
B161.93
PX_10-DS-5183-B21A-T
PIPE-10 FROM VD-1641A TO CL-348
C100.01
PX_20-FG-28014-B22A-H
PIPE->16 FROM HE-113B TO PP-958B
C100.01
PX_ROF-307A
MP STEAM TO PP-1984A
C100.00

Lead time and procurement

Lead time 71 ± 60 days (PO history, 19 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
15 Aug 2026PR03
Regular replenishment
42Rp 207,96824 Sept 202640 d
05 Aug 2026PR03
Regular replenishment
33Rp 202,86109 Sept 202635 d
04 Aug 2026PR03
Regular replenishment
32Rp 209,61831 Aug 202627 d
11 Jul 2026PR06
Regular replenishment
19Rp 207,83421 Sept 202672 d
25 Jun 2026PR03
Regular replenishment
58Rp 214,42910 Aug 202646 d
20 Feb 2026PR05
Project / turnaround
60Rp 209,61514 Apr 202653 d
18 Feb 2026PR06
Regular replenishment
53Rp 197,93628 Mar 202638 d
18 Jan 2026PR01
Import / long-lead
19Rp 199,77916 Oct 2026
open
271 d
27 Dec 2025PR03
Regular replenishment
59Rp 210,77508 Feb 202643 d
01 Nov 2025PR03
Regular replenishment
30Rp 210,39013 Dec 202542 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
20 Aug 2026LowPX_HE-902Cleaning HE-902
11 Aug 2026MediumPX_HE-902Install scaffolding at HE-902
31 Mar 2026MediumPX_HE-902Cleaning HE-902
05 Dec 2025MediumPX_HE-902Replace lamp as per PM finding
17 Nov 2025MediumPX_HE-902HE-902 tube leak
29 May 2025MediumPX_HE-902Install scaffolding at HE-902

Recent goods issues

Posting dateQtyOrderOrder type
06 Jul 20261201000026474Corrective
11 Jun 20261201000026975Corrective
07 Jun 20261201000019688Corrective
31 May 20261204000015505Preventive
10 May 20262201000002115Corrective
31 Mar 20265204000008605Preventive
30 Mar 202611201000001342Corrective
10 Feb 202620203000018609Turnaround
03 Feb 20262201000009533Corrective
30 Jan 20261201000005004Corrective
24 Jan 20266201000038629Corrective
12 Jan 20266201000039896Corrective
30 Dec 20253201000000962Corrective
27 Dec 202516203000006078Turnaround
17 Dec 20253201000038754Corrective