Sparely
DU

FLANGE,WN,10IN,300#,A105,RF

Material 4100033097 · FLANGE · Plant 1000

CMonitorSlow-moving
Material
4100033097
Category
FLANGE
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 2 FuncLocs A/B)
Supplier
RAJAWALI INSTRUMEN INTERNASIONAL PT
Lead time
47 d · P80 78 d
Unit price
Rp 955,395

Recommendation

  • 1.Forecast 6.8 EA/year: 6.8 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~47 days; expected demand during lead time 0.9.
  • 3.A 87.7% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 7.
Single source
On hand / on order
5 / 0
no open PO
Today Min / Max
4 / 6
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
7
order qty 7
Service level
87.7%
stockout risk now 12%
Unit price
Rp 955,395
PO history
ML early warning: 20% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 272 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 9.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~19 days.

Installed on 2 functional locations

0 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_HE-235A
DEMIN WATER CONDENSER
C110.22
PX_1-1/2-QO-5213-A41A-HS
PIPE-1-1/2 FROM PP-1952A TO PP-1872A
C100.01

Lead time and procurement

Lead time 47 ± 25 days (PO history + category, 2 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
31 May 2026PR03
Regular replenishment
9Rp 925,88427 Jul 202657 d
09 Dec 2025PR03
Regular replenishment
3Rp 984,90527 Jan 202649 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 May 2025MediumPY_HE-235APSM25/HE-235A tube leak

Recent goods issues

Posting dateQtyOrderOrder type
02 Jan 20262201000009091Corrective
02 Jan 20268201000009091Corrective
01 Jan 20266201000009091Corrective
23 Nov 20254201000004058Corrective