FLANGE,WN,10IN,300#,SS316,RF
Material 4100033123 · FLANGE · Plant 1000
AReduceSlow-moving
- Material
- 4100033123
- Category
- FLANGE
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (2 of 6 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 43 d · P80 78 d
- Unit price
- Rp 927,596 (est.)
Recommendation
- 1.Forecast 3.2 EA/year: 3.2 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~43 days; expected demand during lead time 0.4.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 9, order up to 14.
- 4.Stock 22 exceeds the level to keep (14) by 8.
- 5.Installed on 6 FuncLoc(s), 2 of them criticality A/B.
Convert to Stock ItemPrice estimatedLead time estimated
On hand / on order
22 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
9
safety stock 9
Rec. Max
14
order qty 5
Service level
100.0%
stockout risk now 0%
Unit price
Rp 927,596
Category + unit estimate
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 331 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 281.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~19 days.
Installed on 6 functional locations
2 with criticality A/B · 7 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_HE-563 CAUSTIC TLE | A | 1 | 0 | 0.22 |
| PX_HE-895B DEMIN WATER EXCHANGER | A | 1 | 0 | 0.22 |
| PX_HE-1727 LUBE OIL COOLER | C | 1 | 3 | 1.08 |
| PX_10-BF-13397-D12A-H PIPE-10 FROM PP-681B TO VD-793A | C | 2 | 1 | 0.01 |
| PX_2-P-13414-C11A-H PIPE-2 FROM KC-452 TO HE-418 | C | 1 | 0 | 0.01 |
| PX_3-QO-22033-A41A-H PIPE-3 FROM VD-958 TO VD-783 | C | 1 | 0 | 0.01 |
Lead time and procurement
Lead time 43 ± 25 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 13 May 2026 | Medium | PX_HE-1727 | HE-1727 fouling |
| 22 Sept 2025 | Medium | PX_HE-1727 | HE-1727 fouling |
| 30 May 2025 | Low | PX_10-BF-13397-D12A-H | Replace lamp as per PM finding |
| 12 May 2025 | Medium | PX_HE-1727 | Retubing HE-1727 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 04 Nov 2025 | 6 | 201000008280 | Corrective |
| 12 Jul 2025 | 3 | 204000010232 | Preventive |