FLANGE,WN,2IN,150#,A105,RF
Material 4100033191 · FLANGE · Plant 1000
AMonitorInsurance gap
- Material
- 4100033191
- Category
- FLANGE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 43 d · P80 78 d
- Unit price
- Rp 927,596 (est.)
Recommendation
- 1.Forecast 0.9 EA/year: 0.9 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~43 days; expected demand during lead time 0.1.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 10.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
10 / 21
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
10
order qty 5
Service level
100.0%
stockout risk now 2%
Unit price
Rp 927,596
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 84.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~19 days.
Installed on 3 functional locations
1 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_HE-1660A REFLUX CONDENSER | A | 1 | 5 | 2.36 |
| PX_HE-1396C PROPYLENE TLE | C | 1 | 7 | 2.79 |
| PX_3/4-CW-27934-A51A-T PIPE-3/4 FROM KC-930C TO PP-506A | C | 1 | 0 | 0.01 |
Lead time and procurement
Lead time 43 ± 25 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 17 Sept 2026 | Medium | PX_HE-1396C | [MSI-B-26-NWH-385] Permanent repair |
| 15 Sept 2026 | Emergency | PX_HE-1660A | [MSI-B-26-ZCD-129] Permanent repair |
| 15 Jun 2026 | Medium | PX_HE-1396C | [MSI-B-26-DDD-161] Permanent repair |
| 22 Apr 2026 | Low | PX_HE-1396C | Retubing HE-1396C |
| 03 Apr 2026 | High | PX_HE-1396C | Cleaning HE-1396C |
| 25 Mar 2026 | Medium | PX_HE-1660A | Cleaning HE-1660A |
| 10 Feb 2026 | Medium | PX_HE-1396C | HE-1396C fouling |
| 13 Jan 2026 | Medium | PX_HE-1660A | Leak from packing |
| 07 Nov 2025 | Medium | PX_HE-1396C | Leak from packing |
| 13 Sept 2025 | Medium | PX_HE-1660A | Cleaning HE-1660A |
Recent goods issues
Never issued in the 17-month history.