FLANGE,BLIND,4IN,300#,A105,RF

Material 4100033359 · FLANGE · Plant 1000

AMonitorInsurance gap
Material
4100033359
Category
FLANGE
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
43 d · P80 78 d
Unit price
Rp 927,596 (est.)

Recommendation

  • 1.Forecast 0.5 EA/year: 0.5 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~43 days; expected demand during lead time 0.1.
  • 3.A 98.8% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 5.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
5
order qty 5
Service level
98.8%
stockout risk now 1%
Unit price
Rp 927,596
Category + unit estimate
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 42.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~19 days.

Installed on 5 functional locations

2 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_HE-1074
C3 RECYCLE REBOILER
A131.08
PX_1-HS-14342-A22A-H
PIPE-1 FROM HE-278D TO PP-1543
A100.01
PY_HE-236B
SEAL OIL CONDENSER
C151.50
PX_16-FG-21944-B23A-T
PIPE->16 FROM PP-280A TO PP-448
C100.01
PX_ROF-1593A
RESTRICTION ORIFICE
C100.00

Lead time and procurement

Lead time 43 ± 25 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Jul 2026MediumPY_HE-236BHE-236B fouling
02 Jul 2026LowPX_HE-1074Install scaffolding at HE-1074
22 Mar 2026LowPX_HE-1074Cleaning HE-1074
11 Feb 2026MediumPY_HE-236BCleaning HE-236B
29 Oct 2025MediumPY_HE-236BLeak from packing
07 Oct 2025MediumPY_HE-236BInstall scaffolding at HE-236B
01 Jun 2025HighPX_HE-1074Leak from packing
30 May 2025MediumPY_HE-236BCleaning HE-236B

Recent goods issues

Never issued in the 17-month history.