VALVE,GATE,1-1/2IN,300#,CF8,RF
Material 4100034556 · VALVE · Plant 1000
ALong-leadReduceExcess
- Material
- 4100034556
- Category
- VALVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (19 of 46 FuncLocs A/B)
- Supplier
- CAHAYA INDUSTRI SENTOSA PT
- Lead time
- 75 d · P80 102 d
- Unit price
- Rp 7.8M
Recommendation
- 1.Forecast 197 EA/year: 197 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~75 days; expected demand during lead time 40.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 101, order up to 121.
- 4.Stock 287 exceeds the level to keep (121) by 166.
- 5.Long lead time: 80% of deliveries took up to 102 days and the fastest seen in its category 20 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 46 FuncLoc(s), 19 of them criticality A/B.
- 7.ML early warning: 100% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 28Single sourceAbnormal consumptionOpen PO
On hand / on order
287 / 1,326
next delivery 04 Oct 2026
Today Min / Max
82 / 247
static parameters in BoM
Rec. Min (reorder point)
101
safety stock 61
Rec. Max
121
order qty 20
Service level
99.9%
stockout risk now 0%
Unit price
Rp 7.8M
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 56 issue days in the last 180 days, last issue 1 days ago, 111 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 21 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (34 units) excluded from the baseline.
Demand pattern Smooth · 179 issue days · 21 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 51.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.
Installed on 46 functional locations
19 with criticality A/B · 59 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 1 | 114 | 42.86 |
| PX_BF-106 CRACKING FURNACE BF-106 | A | 1 | 82 | 30.86 |
| PX_BF-112 CRACKING FURNACE BF-112 | A | 1 | 73 | 27.01 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 1 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 1 | 38 | 14.58 |
| PX_BF-109 CRACKING FURNACE BF-109 | A | 3 | 29 | 11.58 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 4 | 28 | 11.58 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 1 | 23 | 9.01 |
| PY_VD-1557A RICH AMINE SEPARATOR | A | 1 | 2 | 0.08 |
| PX_3/4-IA-29930-A22A-T PIPE-3/4 FROM HE-1217C TO HE-1774A | A | 1 | 0 | 0.01 |
| PX_VD-1822 QUENCH OIL SURGE DRUM | A | 1 | 0 | 0.08 |
| PX_VD-749A PROPYLENE SEPARATOR | A | 1 | 0 | 0.08 |
Lead time and procurement
Lead time 75 ± 32 days (PO history, 57 PO lines) · on-time 42%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 21 Sept 2026 | PR04 Regular (other) | 127 | Rp 7.7M | 01 Jan 2027 open | 102 d |
| 07 Sept 2026 | PR03 Regular replenishment | 156 | Rp 7.5M | 11 Nov 2026 open | 65 d |
| 30 Aug 2026 | PR03 Regular replenishment | 133 | Rp 7.8M | 04 Dec 2026 open | 96 d |
| 24 Aug 2026 | PR03 Regular replenishment | 144 | Rp 8.0M | 27 Nov 2026 open | 95 d |
| 17 Aug 2026 | PR06 Regular replenishment | 93 | Rp 7.8M | 10 Oct 2026 open | 54 d |
| 17 Aug 2026 | PR03 Regular replenishment | 120 | Rp 8.0M | 09 Oct 2026 open | 53 d |
| 10 Aug 2026 | PR03 Regular replenishment | 142 | Rp 8.0M | 09 Nov 2026 open | 91 d |
| 04 Aug 2026 | PR03 Regular replenishment | 87 | Rp 7.6M | 04 Oct 2026 open | 61 d |
| 26 Jul 2026 | PR03 Regular replenishment | 84 | Rp 7.8M | 01 Nov 2026 open | 98 d |
| 17 Jul 2026 | PR03 Regular replenishment | 157 | Rp 7.7M | 15 Aug 2026 | 29 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 1 | 201000012524 | Corrective |
| 30 Sept 2026 | 1 | 201000017495 | Corrective |
| 26 Sept 2026 | 4 | 209000029477 | Other maintenance |
| 22 Sept 2026 | 1 | 201000006563 | Corrective |
| 22 Sept 2026 | 2 | 204000002989 | Preventive |
| 21 Sept 2026 | 1 | 201000006305 | Corrective |
| 19 Sept 2026 | 1 | 201000024840 | Corrective |
| 17 Sept 2026 | 1 | 201000022353 | Corrective |
| 14 Sept 2026 | 1 | 201000010974 | Corrective |
| 10 Sept 2026 | 1 | 204000002121 | Preventive |
| 06 Sept 2026 | 4 | 201000031451 | Corrective |
| 28 Aug 2026 | 2 | 201000007926 | Corrective |
| 24 Aug 2026 | 1 | 201000000994 | Corrective |
| 15 Aug 2026 | 1 | 204000039855 | Preventive |
| 13 Aug 2026 | 2 | 201000031702 | Corrective |