VALVE,GATE,2IN,800#,A216WCB,SW

Material 4100034613 · VALVE · Plant 1000

AMonitorHealthy
Material
4100034613
Category
VALVE
Base unit
EA
MRP type
Stock Item
Criticality
A (5 of 12 FuncLocs A/B)
Supplier
BINTANG MESINDO PRATAMA PT
Lead time
31 d · P80 38 d
Unit price
Rp 2.9M

Recommendation

  • 1.Forecast 43 EA/year: 43 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~31 days; expected demand during lead time 3.6.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 13, order up to 28.
  • 4.Installed on 12 FuncLoc(s), 5 of them criticality A/B.
  • 5.ML early warning: 100% probability of demand in the next 90 days.
ML early warningLast turnaround used 14Single sourceAbnormal consumptionOpen PO
On hand / on order
6 / 19
next delivery 08 Oct 2026
Today Min / Max
5 / 14
static parameters in BoM
Rec. Min (reorder point)
13
safety stock 10
Rec. Max
28
order qty 15
Service level
100.0%
stockout risk now 0%
Unit price
Rp 2.9M
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 12 issue days in the last 180 days, last issue 7 days ago, 16 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 7 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (21 units) excluded from the baseline.

Demand pattern Erratic · 52 issue days · 3 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 13.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.

Installed on 12 functional locations

5 with criticality A/B · 12 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-112
CRACKING FURNACE BF-112
A17327.01
PX_BF-111
CRACKING FURNACE BF-111
A1239.01
PX_VD-1252
METHANE ACCUMULATOR
A100.08
PX_VD-341
GASOLINE SURGE DRUM
A100.08
PX_VD-884A
RECYCLE ETHANE SEPARATOR
B100.08
PX_VD-1208
FUEL OIL KO DRUM
C131.36
PX_3/4-FG-13739-A41A-C
PIPE-3/4 FROM PP-1541 TO HE-980D
C100.01
PX_3/4-FG-9721-A11A-T
PIPE-3/4 FROM HE-1365D TO KC-778A
C100.01
PX_3/4-P-6518-A41A-HS
PIPE-3/4 FROM KC-669 TO HE-1808D
C100.01
PX_8-CW-21089-A51A-C
PIPE-8 FROM PP-128C TO PP-319
C100.01
PX_8-P-13643-B21A-T
PIPE-8 FROM HE-1797C TO PP-256
C100.01
PX_BF-101
CRACKING FURNACE BF-101
S183.02

Lead time and procurement

Lead time 31 ± 16 days (PO history, 22 PO lines) · on-time 49%

PR dateTypeQtyUnit priceDeliveryLead time
31 Aug 2026PR03
Regular replenishment
19Rp 3.0M08 Oct 2026
open
38 d
01 Aug 2026PR06
Regular replenishment
41Rp 2.9M20 Aug 202619 d
30 May 2026PR05
Project / turnaround
38Rp 2.9M24 Jul 202655 d
17 May 2026PR06
Regular replenishment
36Rp 2.9M11 Jun 202625 d
16 May 2026PR06
Regular replenishment
41Rp 3.0M23 Jun 202638 d
27 Apr 2026PR03
Regular replenishment
40Rp 3.0M28 Jun 202662 d
08 Apr 2026PR03
Regular replenishment
13Rp 2.9M29 Apr 202621 d
28 Mar 2026PR03
Regular replenishment
17Rp 2.8M15 Apr 202618 d
05 Jan 2026PR06
Regular replenishment
23Rp 2.9M20 Jan 202615 d
28 Dec 2025PR03
Regular replenishment
23Rp 2.8M19 Jan 202622 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_BF-112Install cover plate BF-112
29 Sept 2026LowPX_BF-112Painting BF-112
27 Sept 2026MediumPX_BF-112Repair insulation BF-112
22 Sept 2026MediumPX_BF-111Install cover plate BF-111
17 Sept 2026MediumPX_BF-112Cleaning burner BF-112
14 Sept 2026MediumPX_BF-101Replace lamp as per PM finding
10 Sept 2026MediumPX_BF-111Peep door broken BF-111
04 Sept 2026HighPX_BF-112Install scaffolding at BF-112
01 Sept 2026MediumPX_BF-112Replace burner tip BF-112
01 Sept 2026MediumPX_BF-112Replace burner tip BF-112

Recent goods issues

Posting dateQtyOrderOrder type
24 Sept 20262201000006497Corrective
24 Sept 20261201000008900Corrective
17 Sept 20261209000036917Other maintenance
12 Sept 20263201000010974Corrective
16 Aug 20261209000023087Other maintenance
23 Jul 20261201000015695Corrective
16 Jun 20263201000024271Corrective
07 Jun 20261204000030837Preventive
24 May 20264201000023907Corrective
17 May 20261201000039669Corrective
06 May 20261201000029629Corrective
15 Apr 20261201000039591Corrective
08 Apr 20261201000001052Corrective
16 Mar 20261201000018051Corrective
28 Feb 20261201000006302Corrective