VALVE,GATE,6IN,300#,A105,SW
Material 4100034648 · VALVE · Plant 1000
AReduceExcess
- Material
- 4100034648
- Category
- VALVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 5 FuncLocs A/B)
- Supplier
- SAMUDRA SEJAHTERA INTERNASIONAL PT
- Lead time
- 46 d · P80 56 d
- Unit price
- Rp 4.6M
Recommendation
- 1.Forecast 37 EA/year: 37 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~46 days; expected demand during lead time 4.6.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 18, order up to 29.
- 4.Stock 446 exceeds the level to keep (29) by 417.
- 5.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
- 6.ML early warning: 100% probability of demand in the next 90 days.
ML early warningLast turnaround used 5Single source
On hand / on order
446 / 0
no open PO
Today Min / Max
8 / 22
static parameters in BoM
Rec. Min (reorder point)
18
safety stock 14
Rec. Max
29
order qty 11
Service level
99.9%
stockout risk now 0%
Unit price
Rp 4.6M
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 11 issue days in the last 180 days, last issue 12 days ago, 10 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 5 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (9 units) excluded from the baseline.
Demand pattern Smooth · 42 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 10.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.
Installed on 5 functional locations
2 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-104 CRACKING FURNACE BF-104 | A | 1 | 28 | 11.58 |
| PX_VD-1465A GASOLINE ACCUMULATOR | A | 1 | 2 | 0.51 |
| PX_1-IA-22130-A22A PIPE-1 FROM KC-586 TO VD-1232 | C | 1 | 0 | 0.01 |
| PX_12-DS-1597-A11A-T PIPE-12 FROM HE-193B TO HE-880A | C | 1 | 0 | 0.01 |
| PX_12-LS-11671-C11A-T PIPE-12 FROM KC-228B TO VD-1974D | C | 1 | 0 | 0.01 |
Lead time and procurement
Lead time 46 ± 31 days (PO history, 20 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 31 Jul 2026 | PR06 Regular replenishment | 15 | Rp 4.5M | 08 Sept 2026 | 39 d |
| 23 Jul 2026 | PR06 Regular replenishment | 21 | Rp 4.8M | 22 Aug 2026 | 30 d |
| 23 Jul 2026 | PR06 Regular replenishment | 11 | Rp 4.5M | 29 Aug 2026 | 37 d |
| 06 Jun 2026 | PR03 Regular replenishment | 23 | Rp 4.7M | 18 Sept 2026 | 104 d |
| 20 May 2026 | PR06 Regular replenishment | 26 | Rp 4.5M | 21 Jun 2026 | 32 d |
| 03 Apr 2026 | PR06 Regular replenishment | 10 | Rp 4.7M | 06 May 2026 | 33 d |
| 21 Feb 2026 | PR03 Regular replenishment | 34 | Rp 4.6M | 25 Mar 2026 | 32 d |
| 01 Jan 2026 | PR05 Project / turnaround | 28 | Rp 4.6M | 01 Jun 2026 | 151 d |
| 23 Dec 2025 | PR06 Regular replenishment | 31 | Rp 4.7M | 19 Feb 2026 | 58 d |
| 20 Nov 2025 | PR03 Regular replenishment | 13 | Rp 4.7M | 16 Dec 2025 | 26 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 16 Sept 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
| 13 Sept 2026 | Low | PX_BF-104 | Install cover plate for MCP cracking |
| 04 Sept 2026 | Medium | PX_BF-104 | Replace burner tip BF-104 |
| 01 Sept 2026 | Medium | PX_BF-104 | Install scaffolding at BF-104 |
| 29 Aug 2026 | High | PX_BF-104 | Leak from packing |
| 08 Aug 2026 | Low | PX_BF-104 | [MSI-B-26-MZB-191] Permanent repair |
| 04 Aug 2026 | Medium | PX_BF-104 | Thermograph wall BF-104 |
| 04 Aug 2026 | Medium | PX_BF-104 | Peep door broken BF-104 |
| 21 Jul 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 19 Sept 2026 | 2 | 201000017105 | Corrective |
| 04 Sept 2026 | 1 | 201000031484 | Corrective |
| 31 Aug 2026 | 1 | 203000017844 | Turnaround |
| 27 Jul 2026 | 1 | 201000029643 | Corrective |
| 23 Jul 2026 | 1 | 201000026095 | Corrective |
| 07 Jul 2026 | 1 | 201000035798 | Corrective |
| 25 Jun 2026 | 1 | 201000016931 | Corrective |
| 09 Jun 2026 | 3 | 209000008419 | Other maintenance |
| 01 Jun 2026 | 1 | 201000010191 | Corrective |
| 22 May 2026 | 1 | 201000022307 | Corrective |
| 17 May 2026 | 1 | 201000009393 | Corrective |
| 27 Apr 2026 | 1 | 201000022540 | Corrective |
| 23 Mar 2026 | 1 | 201000009275 | Corrective |
| 21 Mar 2026 | 1 | 201000019771 | Corrective |
| 15 Feb 2026 | 1 | 204000026249 | Preventive |