VALVE,GATE,1/2IN,300#,A216WCB,RF
Material 4100034656 · VALVE · Plant 1000
ALong-leadReduceExcess
- Material
- 4100034656
- Category
- VALVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (6 of 11 FuncLocs A/B)
- Supplier
- GEMILANG LOGAM MAKMUR PT
- Lead time
- 89 d · P80 157 d
- Unit price
- Rp 1.2M
Recommendation
- 1.Forecast 33 EA/year: 33 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~89 days; expected demand during lead time 8.0.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 34, order up to 54.
- 4.Stock 129 exceeds the level to keep (54) by 75.
- 5.Long lead time: 80% of deliveries took up to 157 days and the fastest seen in its category 20 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 11 FuncLoc(s), 6 of them criticality A/B.
- 7.ML early warning: 100% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 4Single sourceAbnormal consumptionOpen PO
On hand / on order
129 / 50
next delivery 19 Oct 2026
Today Min / Max
2 / 3
static parameters in BoM
Rec. Min (reorder point)
34
safety stock 27
Rec. Max
54
order qty 20
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.2M
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 8 issue days in the last 180 days, last issue 16 days ago, 39 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 6 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (10 units) excluded from the baseline.
Demand pattern Smooth · 35 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 9.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.
Installed on 11 functional locations
6 with criticality A/B · 14 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-102 CRACKING FURNACE BF-102 | A | 4 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 1 | 38 | 14.58 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 1 | 28 | 11.58 |
| PX_3/4-P-10242-A51A-T PIPE-3/4 FROM PP-1407B TO BF-104 | A | 1 | 0 | 0.01 |
| PX_VD-939 BOTTOM SURGE DRUM | A | 1 | 0 | 0.08 |
| PX_VD-914 LEAN AMINE ACCUMULATOR | B | 1 | 5 | 0.93 |
| PX_1-FG-8131-A51A-H PIPE-1 FROM VD-213 TO HE-536 | C | 1 | 1 | 0.44 |
| PX_VD-1192 FLUSHING OIL ACCUMULATOR | C | 1 | 1 | 0.08 |
| PX_1-DS-4855-A51A-C PIPE-1 FROM HE-1277C TO PP-438B | C | 1 | 0 | 0.01 |
| PX_2-QO-8042-C11A-H PIPE-2 FROM VD-1209A TO VD-958 | C | 1 | 0 | 0.01 |
| PX_VD-1129 SEAL OIL SURGE DRUM | C | 1 | 0 | 0.08 |
Lead time and procurement
Lead time 89 ± 81 days (PO history, 13 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 19 Sept 2026 | PR03 Regular replenishment | 16 | Rp 1.2M | 08 Nov 2026 open | 50 d |
| 13 Sept 2026 | PR06 Regular replenishment | 13 | Rp 1.2M | 19 Oct 2026 open | 36 d |
| 22 Jun 2026 | PR03 Regular replenishment | 20 | Rp 1.2M | 15 Jul 2026 | 23 d |
| 22 Jun 2026 | PR03 Regular replenishment | 13 | Rp 1.2M | 16 Aug 2026 | 55 d |
| 12 Jun 2026 | PR05 Project / turnaround | 13 | Rp 1.2M | 27 May 2027 open | 349 d |
| 15 May 2026 | PR05 Project / turnaround | 8 | Rp 1.2M | 30 Nov 2026 open | 199 d |
| 15 Feb 2026 | PR05 Project / turnaround | 16 | Rp 1.3M | 12 Aug 2026 | 178 d |
| 13 Feb 2026 | PR03 Regular replenishment | 20 | Rp 1.3M | 20 Apr 2026 | 66 d |
| 09 Oct 2025 | PR03 Regular replenishment | 17 | Rp 1.2M | 02 Dec 2025 | 54 d |
| 26 Sept 2025 | PR03 Regular replenishment | 26 | Rp 1.3M | 14 Nov 2025 | 49 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 16 Sept 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
| 15 Sept 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
| 14 Sept 2026 | Medium | PX_VD-914 | Leak from packing |
| 13 Sept 2026 | Low | PX_BF-104 | Install cover plate for MCP cracking |
| 11 Sept 2026 | Medium | PX_BF-103 | Decoking follow up BF-103 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 15 Sept 2026 | 1 | 201000001040 | Corrective |
| 04 Aug 2026 | 2 | 205000008171 | Other maintenance |
| 03 Aug 2026 | 1 | 204000030240 | Preventive |
| 04 Jul 2026 | 2 | 201000023359 | Corrective |
| 19 Jun 2026 | 1 | 201000018305 | Corrective |
| 08 Jun 2026 | 1 | 201000025799 | Corrective |
| 20 May 2026 | 2 | 201000027299 | Corrective |
| 23 Apr 2026 | 1 | 201000030822 | Corrective |
| 01 Apr 2026 | 1 | 201000026925 | Corrective |
| 21 Mar 2026 | 1 | 201000019771 | Corrective |
| 04 Mar 2026 | 1 | 201000025419 | Corrective |
| 23 Feb 2026 | 1 | 201000036183 | Corrective |
| 19 Feb 2026 | 1 | 201000019173 | Corrective |
| 19 Feb 2026 | 1 | 201000023270 | Corrective |
| 07 Feb 2026 | 4 | 203000032991 | Turnaround |