VALVE,GATE,1/2IN,300#,A216WCB,RF

Material 4100034656 · VALVE · Plant 1000

ALong-leadReduceExcess
Material
4100034656
Category
VALVE
Base unit
EA
MRP type
Stock Item
Criticality
A (6 of 11 FuncLocs A/B)
Supplier
GEMILANG LOGAM MAKMUR PT
Lead time
89 d · P80 157 d
Unit price
Rp 1.2M

Recommendation

  • 1.Forecast 33 EA/year: 33 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~89 days; expected demand during lead time 8.0.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 34, order up to 54.
  • 4.Stock 129 exceeds the level to keep (54) by 75.
  • 5.Long lead time: 80% of deliveries took up to 157 days and the fastest seen in its category 20 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 11 FuncLoc(s), 6 of them criticality A/B.
  • 7.ML early warning: 100% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 4Single sourceAbnormal consumptionOpen PO
On hand / on order
129 / 50
next delivery 19 Oct 2026
Today Min / Max
2 / 3
static parameters in BoM
Rec. Min (reorder point)
34
safety stock 27
Rec. Max
54
order qty 20
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.2M
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 8 issue days in the last 180 days, last issue 16 days ago, 39 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 6 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (10 units) excluded from the baseline.

Demand pattern Smooth · 35 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 9.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.

Installed on 11 functional locations

6 with criticality A/B · 14 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-102
CRACKING FURNACE BF-102
A47128.72
PX_BF-103
CRACKING FURNACE BF-103
A13814.58
PX_BF-104
CRACKING FURNACE BF-104
A12811.58
PX_3/4-P-10242-A51A-T
PIPE-3/4 FROM PP-1407B TO BF-104
A100.01
PX_VD-939
BOTTOM SURGE DRUM
A100.08
PX_VD-914
LEAN AMINE ACCUMULATOR
B150.93
PX_1-FG-8131-A51A-H
PIPE-1 FROM VD-213 TO HE-536
C110.44
PX_VD-1192
FLUSHING OIL ACCUMULATOR
C110.08
PX_1-DS-4855-A51A-C
PIPE-1 FROM HE-1277C TO PP-438B
C100.01
PX_2-QO-8042-C11A-H
PIPE-2 FROM VD-1209A TO VD-958
C100.01
PX_VD-1129
SEAL OIL SURGE DRUM
C100.08

Lead time and procurement

Lead time 89 ± 81 days (PO history, 13 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
19 Sept 2026PR03
Regular replenishment
16Rp 1.2M08 Nov 2026
open
50 d
13 Sept 2026PR06
Regular replenishment
13Rp 1.2M19 Oct 2026
open
36 d
22 Jun 2026PR03
Regular replenishment
20Rp 1.2M15 Jul 202623 d
22 Jun 2026PR03
Regular replenishment
13Rp 1.2M16 Aug 202655 d
12 Jun 2026PR05
Project / turnaround
13Rp 1.2M27 May 2027
open
349 d
15 May 2026PR05
Project / turnaround
8Rp 1.2M30 Nov 2026
open
199 d
15 Feb 2026PR05
Project / turnaround
16Rp 1.3M12 Aug 2026178 d
13 Feb 2026PR03
Regular replenishment
20Rp 1.3M20 Apr 202666 d
09 Oct 2025PR03
Regular replenishment
17Rp 1.2M02 Dec 202554 d
26 Sept 2025PR03
Regular replenishment
26Rp 1.3M14 Nov 202549 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
23 Sept 2026LowPX_BF-102Replace burner tip BF-102
21 Sept 2026MediumPX_BF-104Cleaning burner BF-104
20 Sept 2026MediumPX_BF-103Leak from packing
19 Sept 2026LowPX_BF-103Leak from packing
16 Sept 2026MediumPX_BF-104Hot spot at convection BF-104
15 Sept 2026MediumPX_BF-103Replace lamp as per PM finding
14 Sept 2026MediumPX_VD-914Leak from packing
13 Sept 2026LowPX_BF-104Install cover plate for MCP cracking
11 Sept 2026MediumPX_BF-103Decoking follow up BF-103

Recent goods issues

Posting dateQtyOrderOrder type
15 Sept 20261201000001040Corrective
04 Aug 20262205000008171Other maintenance
03 Aug 20261204000030240Preventive
04 Jul 20262201000023359Corrective
19 Jun 20261201000018305Corrective
08 Jun 20261201000025799Corrective
20 May 20262201000027299Corrective
23 Apr 20261201000030822Corrective
01 Apr 20261201000026925Corrective
21 Mar 20261201000019771Corrective
04 Mar 20261201000025419Corrective
23 Feb 20261201000036183Corrective
19 Feb 20261201000019173Corrective
19 Feb 20261201000023270Corrective
07 Feb 20264203000032991Turnaround