VALVE,GATE,12IN,150#,A216WCB,SW
Material 4100034680 · VALVE · Plant 1000
AReduceExcess
- Material
- 4100034680
- Category
- VALVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (5 of 9 FuncLocs A/B)
- Supplier
- BERKAH ENERGI MAKMUR PT
- Lead time
- 56 d · P80 55 d
- Unit price
- Rp 15.5M
Recommendation
- 1.Forecast 20 EA/year: 20 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~56 days; expected demand during lead time 3.1.
- 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 15.
- 4.Stock 29 exceeds the level to keep (15) by 14.
- 5.Installed on 9 FuncLoc(s), 5 of them criticality A/B.
- 6.ML early warning: 89% probability of demand in the next 90 days.
ML early warningLast turnaround used 3Single sourceAbnormal consumption
On hand / on order
29 / 0
no open PO
Today Min / Max
9 / 13
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 7
Rec. Max
15
order qty 5
Service level
99.5%
stockout risk now 0%
Unit price
Rp 15.5M
PO history
ML early warning: 89% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 6 issue days in the last 180 days, last issue 9 days ago, 11 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (3 units) excluded from the baseline.
Demand pattern Lumpy · 21 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 5.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.
Installed on 9 functional locations
5 with criticality A/B · 9 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-107 CRACKING FURNACE BF-107 | A | 1 | 23 | 9.01 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 1 | 23 | 9.01 |
| PX_VD-1149 SPENT CAUSTIC SURGE DRUM | A | 1 | 4 | 0.93 |
| PX_VD-1416A ETHYLENE SEPARATOR | A | 1 | 0 | 0.08 |
| PX_VD-1291 C4 PRODUCT DRUM | B | 1 | 0 | 0.08 |
| PX_3/4-DS-24384-B22A-T PIPE-3/4 FROM PP-1280B TO HE-234C | C | 1 | 2 | 0.44 |
| PX_1-1/2-QO-17037-B23A PIPE-1-1/2 FROM PP-376A TO HE-263B | C | 1 | 0 | 0.01 |
| PX_3/4-HS-17520-C11A-HS PIPE-3/4 FROM PP-1121 TO VD-468 | C | 1 | 0 | 0.01 |
| PX_3/4-HS-2049-A51A PIPE-3/4 FROM KC-236B TO VD-1976 | C | 1 | 0 | 0.01 |
Lead time and procurement
Lead time 56 ± 42 days (PO history, 12 PO lines) · on-time 47%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 16 Jul 2026 | PR06 Regular replenishment | 11 | Rp 16.0M | 09 Sept 2026 | 55 d |
| 30 Jun 2026 | PR06 Regular replenishment | 14 | Rp 15.5M | 21 Aug 2026 | 52 d |
| 13 Mar 2026 | PR03 Regular replenishment | 15 | Rp 15.3M | 31 Mar 2026 | 18 d |
| 13 Jan 2026 | PR03 Regular replenishment | 15 | Rp 15.6M | 08 Mar 2026 | 54 d |
| 12 Jan 2026 | PR03 Regular replenishment | 13 | Rp 15.7M | 20 Feb 2026 | 39 d |
| 24 Dec 2025 | PR06 Regular replenishment | 13 | Rp 15.8M | 28 Jan 2026 | 35 d |
| 27 Oct 2025 | PR06 Regular replenishment | 6 | Rp 15.3M | 22 Nov 2025 | 26 d |
| 05 Oct 2025 | PR03 Regular replenishment | 17 | Rp 15.4M | 17 Apr 2026 | 194 d |
| 05 Oct 2025 | PR06 Regular replenishment | 9 | Rp 15.6M | 19 Dec 2025 | 75 d |
| 06 Aug 2025 | PR06 Regular replenishment | 13 | Rp 15.0M | 25 Sept 2025 | 50 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 10 Sept 2026 | Medium | PX_BF-111 | Peep door broken BF-111 |
| 08 Sept 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 15 Aug 2026 | Medium | PX_BF-107 | Hot spot at convection BF-107 |
| 08 Aug 2026 | Low | PX_BF-107 | Cleaning burner BF-107 |
| 03 Aug 2026 | Medium | PX_BF-111 | Thermograph wall BF-111 |
| 21 Jul 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 21 Jul 2026 | Medium | PX_BF-107 | Thermograph wall BF-107 |
| 18 Jul 2026 | Emergency | PX_BF-107 | Hot spot at convection BF-107 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 22 Sept 2026 | 2 | 204000002989 | Preventive |
| 24 Jun 2026 | 1 | 201000026692 | Corrective |
| 07 Jun 2026 | 1 | 201000019688 | Corrective |
| 27 May 2026 | 1 | 205000013188 | Other maintenance |
| 17 Apr 2026 | 2 | 201000022069 | Corrective |
| 15 Apr 2026 | 2 | 201000012582 | Corrective |
| 11 Feb 2026 | 1 | 201000014945 | Corrective |
| 06 Feb 2026 | 1 | 201000039107 | Corrective |
| 17 Jan 2026 | 1 | 201000008375 | Corrective |
| 08 Jan 2026 | 1 | 201000017662 | Corrective |
| 26 Dec 2025 | 1 | 201000021137 | Corrective |
| 16 Dec 2025 | 3 | 201000004573 | Corrective |
| 16 Dec 2025 | 2 | 201000006079 | Corrective |
| 14 Dec 2025 | 2 | 201000008016 | Corrective |
| 14 Dec 2025 | 1 | 203000039452 | Turnaround |