VALVE,GATE,4IN,800#,A216WCB,SW
Material 4100034704 · VALVE · Plant 1000
ALong-leadMaintainStockout
- Material
- 4100034704
- Category
- VALVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 5 FuncLocs A/B)
- Supplier
- SAMUDRA SEJAHTERA INTERNASIONAL PT
- Lead time
- 71 d · P80 109 d
- Unit price
- Rp 21.0M
Recommendation
- 1.Forecast 24 EA/year: 24 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~71 days; expected demand during lead time 4.7.
- 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 15, order up to 20.
- 4.Long lead time: 80% of deliveries took up to 109 days and the fastest seen in its category 20 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
- 6.ML early warning: 96% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 2Single sourceOpen PO
On hand / on order
0 / 25
next delivery 04 Oct 2026
Today Min / Max
7 / 21
static parameters in BoM
Rec. Min (reorder point)
15
safety stock 11
Rec. Max
20
order qty 5
Service level
99.6%
stockout risk now 0%
Unit price
Rp 21.0M
PO history
ML early warning: 96% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 10 issue days in the last 180 days, last issue 2 days ago, 22 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (2 units) excluded from the baseline.
Demand pattern Lumpy · 19 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 7.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.
Installed on 5 functional locations
4 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-112 CRACKING FURNACE BF-112 | A | 1 | 73 | 27.01 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 1 | 23 | 9.01 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 1 | 23 | 9.01 |
| PX_VD-1210 C4 PRODUCT ACCUMULATOR | A | 1 | 0 | 0.08 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 1 | 8 | 3.02 |
Lead time and procurement
Lead time 71 ± 43 days (PO history, 12 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 11 Aug 2026 | PR06 Regular replenishment | 11 | Rp 20.9M | 04 Oct 2026 open | 54 d |
| 13 Jul 2026 | PR04 Regular (other) | 10 | Rp 21.7M | 31 Oct 2026 open | 110 d |
| 02 Jun 2026 | PR06 Regular replenishment | 10 | Rp 21.1M | 06 Jul 2026 | 34 d |
| 19 May 2026 | PR04 Regular (other) | 4 | Rp 21.9M | 10 Nov 2026 open | 175 d |
| 24 Mar 2026 | PR06 Regular replenishment | 4 | Rp 20.4M | 02 Jun 2026 | 70 d |
| 23 Feb 2026 | PR01 Import / long-lead | 10 | Rp 20.6M | 10 Jun 2026 | 107 d |
| 25 Nov 2025 | PR06 Regular replenishment | 11 | Rp 21.0M | 26 Dec 2025 | 31 d |
| 10 Nov 2025 | PR03 Regular replenishment | 4 | Rp 20.8M | 03 Jan 2026 | 54 d |
| 24 Oct 2025 | PR05 Project / turnaround | 7 | Rp 21.5M | 18 Feb 2026 | 117 d |
| 30 Aug 2025 | PR06 Regular replenishment | 12 | Rp 21.7M | 21 Sept 2025 | 22 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
| 14 Sept 2026 | Medium | PX_BF-101 | Replace lamp as per PM finding |
| 10 Sept 2026 | Medium | PX_BF-111 | Peep door broken BF-111 |
| 08 Sept 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 04 Sept 2026 | High | PX_BF-112 | Install scaffolding at BF-112 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 29 Sept 2026 | 2 | 201000013476 | Corrective |
| 26 Sept 2026 | 1 | 201000005210 | Corrective |
| 12 Sept 2026 | 1 | 201000020269 | Corrective |
| 30 Jun 2026 | 1 | 209000022177 | Other maintenance |
| 21 Jun 2026 | 1 | 209000014083 | Other maintenance |
| 21 Jun 2026 | 1 | 209000016742 | Other maintenance |
| 17 Jun 2026 | 2 | 201000020554 | Corrective |
| 16 Jun 2026 | 1 | 201000024271 | Corrective |
| 13 Jun 2026 | 2 | 209000014321 | Other maintenance |
| 08 Jun 2026 | 1 | 201000006846 | Corrective |
| 12 Apr 2026 | 2 | 201000017882 | Corrective |
| 01 Feb 2026 | 1 | 201000015284 | Corrective |
| 24 Jan 2026 | 1 | 201000030431 | Corrective |
| 14 Jan 2026 | 2 | 201000007390 | Corrective |
| 02 Jan 2026 | 1 | 201000001557 | Corrective |