VALVE,GATE,1IN,300#,A105,SW
Material 4100034805 · VALVE · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100034805
- Category
- VALVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 8 FuncLocs A/B)
- Supplier
- SURYA INSTRUMEN MAKMUR PT
- Lead time
- 46 d · P80 62 d
- Unit price
- Rp 607,995
Recommendation
- 1.Forecast 11 EA/year: 11 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~46 days; expected demand during lead time 1.4.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 18.
- 4.On hand 4 + on order 0 is at or below the reorder point: order 14 now.
- 5.Installed on 8 FuncLoc(s), 4 of them criticality A/B.
- 6.ML early warning: 84% probability of demand in the next 90 days.
Proposed purchase requisition
14 EA
Rp 8.5M · order by 01 Oct 2026
Expected arrival ≈ 46 days
ML early warningLast turnaround used 7Single source
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
18
order qty 11
Service level
100.0%
stockout risk now 3%
Unit price
Rp 607,995
PO history
ML early warning: 84% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 21 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (8 units) excluded from the baseline.
Demand pattern Lumpy · 16 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.
Installed on 8 functional locations
4 with criticality A/B · 8 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-111 CRACKING FURNACE BF-111 | A | 1 | 23 | 9.01 |
| PY_VD-1070A SLOP OIL DRUM | A | 1 | 2 | 0.51 |
| PX_VD-272 WASH WATER DRUM | A | 1 | 0 | 0.08 |
| PX_16-DS-24185-C11A-T PIPE->16 FROM VD-433 TO VD-1771 | B | 1 | 1 | 0.01 |
| PX_1-BF-4138-C11A-H PIPE-1 FROM HE-600D TO HE-1624 | C | 1 | 0 | 0.01 |
| PX_3-LS-26999-B22A-HS PIPE-3 FROM PP-987A TO PP-1337 | C | 1 | 0 | 0.01 |
| PX_3/4-CW-7128-C11A-H PIPE-3/4 FROM PP-818 TO PP-1404A | C | 1 | 0 | 0.01 |
| PX_8-HS-28263-A41A-H PIPE-8 FROM PP-200A TO HE-1501B | C | 1 | 0 | 0.01 |
Lead time and procurement
Lead time 46 ± 33 days (PO history, 10 PO lines) · on-time 34%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 21 Jul 2026 | PR03 Regular replenishment | 12 | Rp 636,328 | 23 Aug 2026 | 33 d |
| 14 Mar 2026 | PR01 Import / long-lead | 5 | Rp 606,577 | 23 Jul 2026 | 131 d |
| 02 Mar 2026 | PR03 Regular replenishment | 10 | Rp 617,046 | 31 Mar 2026 | 29 d |
| 01 Mar 2026 | PR01 Import / long-lead | 8 | Rp 595,138 | 03 May 2026 | 63 d |
| 25 Feb 2026 | PR03 Regular replenishment | 10 | Rp 614,281 | 24 Mar 2026 | 27 d |
| 18 Feb 2026 | PR03 Regular replenishment | 6 | Rp 635,429 | 11 Mar 2026 | 21 d |
| 06 Feb 2026 | PR03 Regular replenishment | 11 | Rp 595,158 | 10 Mar 2026 | 32 d |
| 20 Oct 2025 | PR06 Regular replenishment | 12 | Rp 609,413 | 12 Nov 2025 | 23 d |
| 21 Sept 2025 | PR06 Regular replenishment | 9 | Rp 593,096 | 22 Nov 2025 | 62 d |
| 15 Jun 2025 | PR03 Regular replenishment | 9 | Rp 604,483 | 22 Jul 2025 | 37 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 10 Sept 2026 | Medium | PX_BF-111 | Peep door broken BF-111 |
| 03 Aug 2026 | Medium | PX_BF-111 | Thermograph wall BF-111 |
| 11 Jul 2026 | Medium | PX_BF-111 | Thermograph wall BF-111 |
| 27 Jun 2026 | Medium | PX_BF-111 | Leak from packing |
| 09 May 2026 | Low | PY_VD-1070A | VD-1070A level glass broken |
| 08 May 2026 | Medium | PX_BF-111 | Repair refractory crack BF-111 |
| 20 Apr 2026 | Emergency | PX_BF-111 | Cleaning burner BF-111 |
| 16 Apr 2026 | Medium | PX_BF-111 | Replace lamp as per PM finding |
| 20 Mar 2026 | Medium | PX_BF-111 | Painting BF-111 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 10 Sept 2026 | 1 | 201000015849 | Corrective |
| 25 Aug 2026 | 1 | 201000012197 | Corrective |
| 13 Jul 2026 | 1 | 201000015079 | Corrective |
| 13 Apr 2026 | 1 | 201000025715 | Corrective |
| 02 Jan 2026 | 1 | 201000024626 | Corrective |
| 21 Dec 2025 | 2 | 203000033807 | Turnaround |
| 20 Dec 2025 | 2 | 201000038011 | Corrective |
| 10 Dec 2025 | 1 | 201000009497 | Corrective |
| 06 Dec 2025 | 1 | 201000006166 | Corrective |
| 06 Dec 2025 | 1 | 203000014228 | Turnaround |
| 04 Dec 2025 | 1 | 201000018271 | Corrective |
| 28 Nov 2025 | 2 | 203000032713 | Turnaround |
| 27 Nov 2025 | 1 | 201000004723 | Corrective |
| 20 Nov 2025 | 2 | 201000032670 | Corrective |
| 14 Nov 2025 | 1 | 206000019278 | Other maintenance |