Sparely
DU

VALVE,GATE,1IN,300#,A105,SW

Material 4100034805 · VALVE · Plant 1000

AReorderNormalBelow reorder point
Material
4100034805
Category
VALVE
Base unit
EA
MRP type
Stock Item
Criticality
A (4 of 8 FuncLocs A/B)
Supplier
SURYA INSTRUMEN MAKMUR PT
Lead time
46 d · P80 62 d
Unit price
Rp 607,995

Recommendation

  • 1.Forecast 11 EA/year: 11 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~46 days; expected demand during lead time 1.4.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 18.
  • 4.On hand 4 + on order 0 is at or below the reorder point: order 14 now.
  • 5.Installed on 8 FuncLoc(s), 4 of them criticality A/B.
  • 6.ML early warning: 84% probability of demand in the next 90 days.
Proposed purchase requisition
14 EA
Rp 8.5M · order by 01 Oct 2026
Expected arrival ≈ 46 days
ML early warningLast turnaround used 7Single source
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
18
order qty 11
Service level
100.0%
stockout risk now 3%
Unit price
Rp 607,995
PO history
ML early warning: 84% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 21 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (8 units) excluded from the baseline.

Demand pattern Lumpy · 16 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.

Installed on 8 functional locations

4 with criticality A/B · 8 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-111
CRACKING FURNACE BF-111
A1239.01
PY_VD-1070A
SLOP OIL DRUM
A120.51
PX_VD-272
WASH WATER DRUM
A100.08
PX_16-DS-24185-C11A-T
PIPE->16 FROM VD-433 TO VD-1771
B110.01
PX_1-BF-4138-C11A-H
PIPE-1 FROM HE-600D TO HE-1624
C100.01
PX_3-LS-26999-B22A-HS
PIPE-3 FROM PP-987A TO PP-1337
C100.01
PX_3/4-CW-7128-C11A-H
PIPE-3/4 FROM PP-818 TO PP-1404A
C100.01
PX_8-HS-28263-A41A-H
PIPE-8 FROM PP-200A TO HE-1501B
C100.01

Lead time and procurement

Lead time 46 ± 33 days (PO history, 10 PO lines) · on-time 34%

PR dateTypeQtyUnit priceDeliveryLead time
21 Jul 2026PR03
Regular replenishment
12Rp 636,32823 Aug 202633 d
14 Mar 2026PR01
Import / long-lead
5Rp 606,57723 Jul 2026131 d
02 Mar 2026PR03
Regular replenishment
10Rp 617,04631 Mar 202629 d
01 Mar 2026PR01
Import / long-lead
8Rp 595,13803 May 202663 d
25 Feb 2026PR03
Regular replenishment
10Rp 614,28124 Mar 202627 d
18 Feb 2026PR03
Regular replenishment
6Rp 635,42911 Mar 202621 d
06 Feb 2026PR03
Regular replenishment
11Rp 595,15810 Mar 202632 d
20 Oct 2025PR06
Regular replenishment
12Rp 609,41312 Nov 202523 d
21 Sept 2025PR06
Regular replenishment
9Rp 593,09622 Nov 202562 d
15 Jun 2025PR03
Regular replenishment
9Rp 604,48322 Jul 202537 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
22 Sept 2026MediumPX_BF-111Install cover plate BF-111
10 Sept 2026MediumPX_BF-111Peep door broken BF-111
03 Aug 2026MediumPX_BF-111Thermograph wall BF-111
11 Jul 2026MediumPX_BF-111Thermograph wall BF-111
27 Jun 2026MediumPX_BF-111Leak from packing
09 May 2026LowPY_VD-1070AVD-1070A level glass broken
08 May 2026MediumPX_BF-111Repair refractory crack BF-111
20 Apr 2026EmergencyPX_BF-111Cleaning burner BF-111
16 Apr 2026MediumPX_BF-111Replace lamp as per PM finding
20 Mar 2026MediumPX_BF-111Painting BF-111

Recent goods issues

Posting dateQtyOrderOrder type
10 Sept 20261201000015849Corrective
25 Aug 20261201000012197Corrective
13 Jul 20261201000015079Corrective
13 Apr 20261201000025715Corrective
02 Jan 20261201000024626Corrective
21 Dec 20252203000033807Turnaround
20 Dec 20252201000038011Corrective
10 Dec 20251201000009497Corrective
06 Dec 20251201000006166Corrective
06 Dec 20251203000014228Turnaround
04 Dec 20251201000018271Corrective
28 Nov 20252203000032713Turnaround
27 Nov 20251201000004723Corrective
20 Nov 20252201000032670Corrective
14 Nov 20251206000019278Other maintenance