VALVE,GATE,10IN,150#,A105,SW
Material 4100035524 · VALVE · Plant 1000
AReorderCriticalSlow-moving
- Material
- 4100035524
- Category
- VALVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 47 d · P80 92 d
- Unit price
- Rp 2.6M (est.)
Recommendation
- 1.Forecast 17 EA/year: 17 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~47 days; expected demand during lead time 2.2.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 15, order up to 25.
- 4.On hand 1 + on order 0 is at or below the reorder point: order 24 now.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
24 EA
Rp 63.1M · order by 01 Oct 2026
Expected arrival ≈ 47 days
Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
15
safety stock 13
Rec. Max
25
order qty 10
Service level
99.9%
stockout risk now 36%
Unit price
Rp 2.6M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 338 days ago, 10 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-104 CRACKING FURNACE BF-104 | A | 1 | 28 | 11.58 |
Lead time and procurement
Lead time 47 ± 30 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 16 Sept 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
| 13 Sept 2026 | Low | PX_BF-104 | Install cover plate for MCP cracking |
| 04 Sept 2026 | Medium | PX_BF-104 | Replace burner tip BF-104 |
| 01 Sept 2026 | Medium | PX_BF-104 | Install scaffolding at BF-104 |
| 29 Aug 2026 | High | PX_BF-104 | Leak from packing |
| 08 Aug 2026 | Low | PX_BF-104 | [MSI-B-26-MZB-191] Permanent repair |
| 04 Aug 2026 | Medium | PX_BF-104 | Thermograph wall BF-104 |
| 04 Aug 2026 | Medium | PX_BF-104 | Peep door broken BF-104 |
| 21 Jul 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 28 Oct 2025 | 5 | 201000001795 | Corrective |