VALVE,NEEDLE,3/4IN ODT,6000PSI,SS316

Material 4100038234 · VALVE · Plant 1000

ALong-leadMonitorHealthy
Material
4100038234
Category
VALVE
Base unit
EA
MRP type
Non Stock
Criticality
A (28 of 60 FuncLocs A/B)
Supplier
SINAR INSTRUMEN NUSANTARA PT
Lead time
91 d · P80 141 d
Unit price
Rp 487,192

Recommendation

  • 1.Forecast 18 EA/year: 18 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~91 days; expected demand during lead time 4.5.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 15, order up to 33.
  • 4.Long lead time: 80% of deliveries took up to 141 days and the fastest seen in its category 20 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 60 FuncLoc(s), 28 of them criticality A/B.
  • 6.ML early warning: 99% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemSingle sourceAbnormal consumptionOpen POSame description as 4 other material numbers
On hand / on order
2 / 20
next delivery 16 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
15
safety stock 11
Rec. Max
33
order qty 18
Service level
100.0%
stockout risk now 0%
Unit price
Rp 487,192
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 7 issue days in the last 180 days, last issue 52 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 6 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Lumpy · 15 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.

Installed on 60 functional locations

28 with criticality A/B · 76 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PIT-1063-22B
PRESSURE
A140.90
PX_TIT-1403D
PP-1309A TEMPERATURE
A130.90
PX_FIT-1992A-33B
PP-1751A INLET FLOW
A100.04
PX_LIT-657
LEVEL
A100.03
PX_LIT-771
KC-671D LEVEL
A100.03
PX_PIT-1253
QUENCH OIL PRESSURE
A100.04
PX_PIT-187
PRESSURE
A400.04
PX_PIT-407A-21B
PP-645A PRESSURE
A100.04
PX_TIT-302A-59A
TEMPERATURE
A100.04
PX_TIT-359
TEMPERATURE
A100.04
PX_DPT-1304-33
PP-818B DP
B120.49
PX_PGI-1323
PP-244A SUCTION
B120.44

Lead time and procurement

Lead time 91 ± 49 days (PO history, 13 PO lines) · on-time 31%

PR dateTypeQtyUnit priceDeliveryLead time
23 Aug 2026PR04
Regular (other)
4Rp 507,01703 Jan 2027
open
133 d
10 Aug 2026PR05
Project / turnaround
9Rp 475,75507 Nov 2026
open
89 d
10 Aug 2026PR06
Regular replenishment
7Rp 479,03516 Oct 2026
open
67 d
28 Jul 2026PR06
Regular replenishment
8Rp 510,39419 Sept 202653 d
10 May 2026PR03
Regular replenishment
6Rp 497,82614 Aug 202696 d
23 Apr 2026PR03
Regular replenishment
15Rp 488,41121 Jun 202659 d
11 Mar 2026PR06
Regular replenishment
7Rp 510,61808 May 202658 d
01 Feb 2026PR05
Project / turnaround
9Rp 486,96121 Aug 2026201 d
20 Dec 2025PR06
Regular replenishment
14Rp 487,19226 Mar 202696 d
09 Sept 2025PR06
Regular replenishment
14Rp 481,34427 Oct 202548 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
27 Sept 2026LowPX_TIT-1403DRepair insulation TIT-1403D
08 Jul 2026LowPX_DPT-1304-33DPT-1304-33 error
21 May 2026LowPX_LIT-925Replace lamp as per PM finding
23 Apr 2026MediumPX_DPT-386Replace lamp as per PM finding
14 Apr 2026LowPX_PIT-1063-22BPainting PIT-1063-22B
09 Apr 2026MediumPX_PGI-1323Replace PGI-1323
07 Apr 2026LowPX_TIT-1403DTIT-1403D abnormal indication
02 Apr 2026MediumPX_PIT-1063-22BAR25/tranmsitter low performance
05 Nov 2025LowPX_PIT-688-21APIT-688-21A error
21 Oct 2025MediumPX_FIT-1591FIT-1591 abnormal indication

Recent goods issues

Posting dateQtyOrderOrder type
10 Aug 20261201000036405Corrective
09 Aug 20261201000036405Corrective
09 Aug 20262201000036405Corrective
13 Jul 20261201000008000Corrective
10 Jul 20261201000004677Corrective
20 Jun 20261204000004159Preventive
31 May 20262204000015505Preventive
11 Apr 20261201000033485Corrective
08 Jan 20262201000024178Corrective
19 Dec 20252201000037452Corrective
15 Dec 20251201000004572Corrective
01 Dec 20251201000038259Corrective
12 Nov 20252201000033206Corrective
03 Oct 20251201000023082Corrective
21 Aug 20252204000016051Preventive