VALVE,NEEDLE,1/4IN NPT,3000PSI,SS316

Material 4100038255 · VALVE · Plant 1000

AMonitorHealthy
Material
4100038255
Category
VALVE
Base unit
EA
MRP type
Stock Item
Criticality
A (12 of 42 FuncLocs A/B)
Supplier
GUNUNG PERKASA NUSANTARA PT
Lead time
30 d · P80 31 d
Unit price
Rp 508,608

Recommendation

  • 1.Forecast 5.0 EA/year: 5.0 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~30 days; expected demand during lead time 0.4.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 9.
  • 4.Installed on 42 FuncLoc(s), 12 of them criticality A/B.
  • 5.ML early warning: 41% probability of demand in the next 90 days.
ML early warningLast turnaround used 1Single sourceOpen POSame description as 5 other material numbers
On hand / on order
2 / 3
next delivery 04 Oct 2026
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
9
order qty 5
Service level
100.0%
stockout risk now 0%
Unit price
Rp 508,608
PO history
ML early warning: 41% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 4 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.

Installed on 42 functional locations

12 with criticality A/B · 49 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PIT-352
HE-1144C PRESSURE
A110.47
PX_FIT-129
METHANOL FLOW
A100.04
PX_FIT-1311-50A
FLOW
A100.04
PX_LIT-527-7
LEVEL
A300.03
PX_PGI-1660-19B
PP-657C SUCTION
A100.02
PX_PIT-450-23
VD-1906 PRESSURE
A100.04
PX_TIT-1655
VD-278A TEMPERATURE
A100.04
PX_LIT-1023-50A
PP-1373A LEVEL
B100.03
PX_LIT-657A
LEVEL
B100.03
PX_PGI-423-26B
VD-749A BTM
B100.02
PX_PIT-1337
PRESSURE
B100.04
PX_PIT-1937
PRESSURE
B100.04

Lead time and procurement

Lead time 30 ± 15 days (PO history, 8 PO lines) · on-time 35%

PR dateTypeQtyUnit priceDeliveryLead time
17 Sept 2026PR03
Regular replenishment
3Rp 528,50704 Oct 2026
open
17 d
14 May 2026PR04
Regular (other)
3Rp 495,86722 Jun 202639 d
13 May 2026PR06
Regular replenishment
3Rp 513,68129 May 202616 d
28 Mar 2026PR03
Regular replenishment
2Rp 528,95316 Apr 202619 d
29 Oct 2025PR03
Regular replenishment
5Rp 503,53522 Nov 202524 d
08 Oct 2025PR03
Regular replenishment
3Rp 499,74825 Oct 202517 d
12 Sept 2025PR03
Regular replenishment
5Rp 523,96106 Oct 202524 d
13 May 2025PR06
Regular replenishment
5Rp 495,53318 Jun 202536 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Sept 2026MediumPX_PIT-758Install scaffolding at PIT-758
09 Sept 2026HighPX_TIT-1562TIT-1562 error
29 Jul 2026HighPX_PIT-758PIT-758 error
04 May 2026MediumPX_PIT-965PIT-965 abnormal indication
29 Dec 2025MediumPX_LIT-948Leak from packing
02 Oct 2025LowPX_LIT-948LIT-948 abnormal indication
25 Sept 2025MediumPX_PIT-758Check PIT-758.ok
28 Aug 2025LowPX_PIT-965Replace lamp as per PM finding
20 Jul 2025HighPX_PIT-352AR25/tranmsitter low performance
05 Jul 2025MediumPX_PGI-1702B-57Replace PGI-1702B-57

Recent goods issues

Posting dateQtyOrderOrder type
27 Sept 20261202000037130Emergency
27 Jan 20261201000013350Corrective
09 Jan 20261201000030970Corrective
22 Dec 20253201000026183Corrective
17 Dec 20251203000037460Turnaround
05 Dec 20251204000007693Preventive
07 Jul 20251201000030225Corrective