VALVE,NEEDLE,1/4IN NPT,6000PSI,SS316
Material 4100038293 · VALVE · Plant 1000
ALong-leadTransferCriticalStockout
- Material
- 4100038293
- Category
- VALVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (7 of 16 FuncLocs A/B)
- Supplier
- SINAR SEJAHTERA LESTARI PT
- Lead time
- 61 d · P80 95 d
- Unit price
- Rp 758,625
Recommendation
- 1.Forecast 1.1 EA/year: 1.1 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~61 days; expected demand during lead time 0.2.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
- 4.On hand 0 + on order 0 is at or below the reorder point: 5 needed.
- 5.Long lead time: 80% of deliveries took up to 95 days and the fastest seen in its category 20 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 16 FuncLoc(s), 7 of them criticality A/B.
- 7.Identical part 4100039028, 4100038706 holds spare stock: transfer 5 EA instead of buying — no purchase needed.
Long-leadSingle sourceSame description as 3 other material numbers
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
100.0%
stockout risk now 11%
Unit price
Rp 758,625
PO history
ML early warning: 17% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 296 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 308.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.
Installed on 16 functional locations
7 with criticality A/B · 16 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PIT-1377 COOLING WATER PRESSURE | A | 1 | 0 | 0.04 |
| PX_TIT-1967 TEMPERATURE | A | 1 | 0 | 0.04 |
| PX_TIT-616 HE-528A TEMPERATURE | A | 1 | 0 | 0.04 |
| PX_PGI-1703 PRESSURE GAUGE | B | 1 | 0 | 0.02 |
| PX_PGI-1790-8A BF-111 DISCHARGE | B | 1 | 0 | 0.02 |
| PX_TIT-1414A TEMPERATURE | B | 1 | 0 | 0.04 |
| PX_TIT-763 TEMPERATURE | B | 1 | 0 | 0.04 |
| PX_PGI-1239 PRESSURE GAUGE | C | 1 | 0 | 0.02 |
| PX_PGI-1673D HE-274C BTM | C | 1 | 0 | 0.02 |
| PX_PGI-690A-46B PP-1101A DISCHARGE | C | 1 | 0 | 0.02 |
| PX_PIT-1095A PRESSURE | C | 1 | 0 | 0.04 |
| PX_PIT-148 LEAN AMINE PRESSURE | C | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 61 ± 34 days (PO history, 3 PO lines) · on-time 33%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 12 Mar 2026 | PR03 Regular replenishment | 2 | Rp 758,625 | 25 Apr 2026 | 44 d |
| 17 Feb 2026 | PR03 Regular replenishment | 2 | Rp 764,789 | 20 Apr 2026 | 62 d |
| 22 Aug 2025 | PR05 Project / turnaround | 1 | Rp 742,490 | 17 Dec 2025 | 117 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Dec 2025 | Medium | PX_TIT-828A-53 | AR25/tranmsitter low performance |
| 07 Jun 2025 | Low | PX_TIT-828A-53 | TIT-828A-53 error |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 09 Dec 2025 | 2 | 201000039227 | Corrective |
| 10 Aug 2025 | 1 | 201000018569 | Corrective |