VALVE,NEEDLE,1/2IN NPT,3000PSI,SS316
Material 4100038374 · VALVE · Plant 1000
ALong-leadReorderNormalBelow reorder point
- Material
- 4100038374
- Category
- VALVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 10 FuncLocs A/B)
- Supplier
- SINAR SEJAHTERA LESTARI PT
- Lead time
- 40 d · P80 92 d
- Unit price
- Rp 2.4M
Recommendation
- 1.Forecast 4.2 EA/year: 4.2 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~40 days; expected demand during lead time 0.5.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 9.
- 4.On hand 1 + on order 0 is at or below the reorder point: order 8 now.
- 5.Long lead time: 80% of deliveries took up to 92 days and the fastest seen in its category 20 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 10 FuncLoc(s), 4 of them criticality A/B.
- 7.ML early warning: 50% probability of demand in the next 90 days.
Proposed purchase requisition
8 EA
Rp 19.4M · order by 01 Oct 2026
Expected arrival ≈ 40 days
Long-leadML early warningSingle source
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
9
order qty 5
Service level
100.0%
stockout risk now 30%
Unit price
Rp 2.4M
PO history
ML early warning: 50% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 99 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 7 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.
Installed on 10 functional locations
4 with criticality A/B · 13 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PGI-1763B VD-706A SUCTION | A | 1 | 1 | 0.02 |
| PX_PIT-1863B-26 PRESSURE | A | 1 | 0 | 0.04 |
| PX_PGI-1499A VD-1044 DISCHARGE | B | 1 | 0 | 0.02 |
| PX_PIT-206 PP-1984A PRESSURE | B | 3 | 0 | 0.04 |
| PX_FIT-947-2B PP-1726 INLET FLOW | C | 1 | 1 | 0.04 |
| PX_PGI-979 HE-771A DISCHARGE | C | 2 | 0 | 0.02 |
| PY_PIT-211-50 LEAN AMINE PRESSURE | C | 1 | 0 | 0.04 |
| PX_DPT-384A DIFF. PRESSURE | S | 1 | 2 | 0.92 |
| PX_DPT-867C VD-531 DP | S | 1 | 0 | 0.06 |
| PX_PIT-1306-27A HE-1817C PRESSURE | S | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 40 ± 30 days (PO history + category, 1 PO lines) · on-time 33%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 12 Aug 2026 | PR06 Regular replenishment | 1 | Rp 2.4M | 30 Aug 2026 | 18 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 08 Nov 2025 | Medium | PX_DPT-384A | AR25/tranmsitter low performance |
| 06 Aug 2025 | Medium | PX_DPT-384A | Replace lamp as per PM finding |
| 18 May 2025 | Medium | PX_FIT-947-2B | Replace lamp as per PM finding |
| 10 May 2025 | Medium | PX_PGI-1763B | Install scaffolding at PGI-1763B |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 24 Jun 2026 | 1 | 201000018159 | Corrective |
| 13 Feb 2026 | 2 | 201000017735 | Corrective |
| 04 Jan 2026 | 1 | 204000035657 | Preventive |
| 16 Dec 2025 | 1 | 201000004572 | Corrective |
| 13 Oct 2025 | 2 | 201000033840 | Corrective |
| 26 Aug 2025 | 1 | 201000037364 | Corrective |
| 25 Aug 2025 | 1 | 201000037364 | Corrective |