VALVE,NEEDLE,1/2IN ODT,6000PSI,SS316

Material 4100038836 · VALVE · Plant 1000

CTransferNormalBelow reorder point
Material
4100038836
Category
VALVE
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 2 FuncLocs A/B)
Supplier
MEGA TEKNIK MAKMUR PT
Lead time
50 d · P80 58 d
Unit price
Rp 559,620

Recommendation

  • 1.Forecast 0.5 EA/year: 0.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~50 days; expected demand during lead time 0.1.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.On hand 1 + on order 0 is at or below the reorder point: 1 needed.
  • 5.Identical part 4100038989 holds spare stock: transfer 1 EA instead of buying — no purchase needed.
Single sourceSame description as 9 other material numbers
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.7%
stockout risk now 0%
Unit price
Rp 559,620
PO history
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 12 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 5.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~20 days.

Installed on 2 functional locations

0 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_LIT-1470
VD-312B LEVEL
C100.03
PX_PIT-1817D-52A
PRESSURE
S100.04

Lead time and procurement

Lead time 50 ± 18 days (PO history, 6 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
01 Aug 2026PR03
Regular replenishment
1Rp 577,20412 Sept 202642 d
15 May 2026PR03
Regular replenishment
2Rp 545,39905 Jul 202651 d
19 Mar 2026PR03
Regular replenishment
1Rp 568,69830 May 202672 d
19 Mar 2026PR03
Regular replenishment
2Rp 540,37216 May 202658 d
22 Nov 2025PR06
Regular replenishment
2Rp 550,54231 Dec 202539 d
16 May 2025PR03
Regular replenishment
2Rp 572,94501 Jul 202546 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
19 Sept 20261201000017105Corrective