VALVE,NEEDLE,1/2IN NPT,6000PSI,SS316
Material 4100038844 · VALVE · Plant 1000
BReduceSlow-moving
- Material
- 4100038844
- Category
- VALVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- B (1 of 5 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 47 d · P80 92 d
- Unit price
- Rp 2.6M (est.)
Recommendation
- 1.Forecast 0.4 EA/year: 0.4 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~47 days; expected demand during lead time 0.1.
- 3.A 98.3% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 3.
- 4.Stock 4 exceeds the level to keep (3) by 1.
- 5.Installed on 5 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimatedSame description as 3 other material numbers
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
3
order qty 3
Service level
98.3%
stockout risk now 0%
Unit price
Rp 2.6M
Category + unit estimate
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 428 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 14.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~20 days.
Installed on 5 functional locations
1 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PGI-1310 HE-1603 SUCTION | B | 1 | 1 | 0.02 |
| PX_LIT-1662 LEVEL | C | 1 | 1 | 0.03 |
| PX_PGI-565 VD-1831 DISCHARGE | C | 1 | 0 | 0.02 |
| PX_PGI-690A-46B PP-1101A DISCHARGE | C | 1 | 0 | 0.02 |
| PX_PGI-1708A HE-322C DISCHARGE | S | 1 | 0 | 0.02 |
Lead time and procurement
Lead time 47 ± 30 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 May 2025 | Medium | PX_LIT-1662 | Install scaffolding at LIT-1662 |
| 20 May 2025 | Medium | PX_PGI-1310 | [MSI-B-25-CHV-140] Permanent repair |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Jul 2025 | 1 | 201000008031 | Corrective |
| 30 Jul 2025 | 2 | 201000008031 | Corrective |