Sparely
DU

CONNECTOR,MALE,1/4IN ODT,1/4IN NPT,SS316

Material 4100040001 · CONNECTOR · Plant 1000

ALong-leadMaintainHealthy
Material
4100040001
Category
CONNECTOR
Base unit
EA
MRP type
Stock Item
Criticality
A (15 of 39 FuncLocs A/B)
Supplier
SINAR SEJAHTERA LESTARI PT
Lead time
54 d · P80 104 d
Unit price
Rp 141,367

Recommendation

  • 1.Forecast 3.4 EA/year: 3.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~54 days; expected demand during lead time 0.5.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 8.
  • 4.Long lead time: 80% of deliveries took up to 104 days and the fastest seen in its category 14 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 39 FuncLoc(s), 15 of them criticality A/B.
  • 6.ML early warning: 48% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 6Single sourceOpen POSame description as 16 other material numbers
On hand / on order
4 / 4
next delivery 23 Oct 2026
Today Min / Max
3 / 6
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
8
order qty 4
Service level
100.0%
stockout risk now 0%
Unit price
Rp 141,367
PO history
ML early warning: 48% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 66 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (6 units) excluded from the baseline.

Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 970.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 39 functional locations

15 with criticality A/B · 47 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FIT-1114
SEAL OIL FLOW
A120.47
PX_TIT-680-43B
HE-1522 TEMPERATURE
A120.04
PX_FIT-218A
VD-1609A INLET FLOW
A100.04
PX_FIT-257
FLOW
A100.04
PX_FIT-303
BFW FLOW
A100.04
PX_LIT-1002
LEVEL
A100.03
PX_LIT-799C
LEVEL
A100.03
PX_PIT-1069
PRESSURE
A100.04
PX_TEL-1791B
TEMPERATURE
A200.01
PX_FIT-1115
HE-605 INLET FLOW
B120.47
PX_LIT-455A-53A
VD-157B LEVEL
B110.46
PX_FIT-627-37A
CL-1319 INLET FLOW
B100.04

Lead time and procurement

Lead time 54 ± 35 days (PO history, 3 PO lines) · on-time 33%

PR dateTypeQtyUnit priceDeliveryLead time
03 Jun 2026PR06
Regular replenishment
4Rp 136,93223 Oct 2026
open
142 d
11 Mar 2026PR03
Regular replenishment
6Rp 141,73826 Apr 202646 d
21 Aug 2025PR06
Regular replenishment
6Rp 141,36708 Oct 202548 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Sept 2026MediumPX_TIT-1681BPainting TIT-1681B
22 Aug 2026LowPX_FIT-1115FIT-1115 error
05 Jun 2026HighPX_TIT-680-43BInstall scaffolding at TIT-680-43B
12 May 2026MediumPX_FIT-1114Replace lamp as per PM finding
29 Dec 2025MediumPX_LIT-948Leak from packing
02 Oct 2025LowPX_LIT-948LIT-948 abnormal indication
09 Sept 2025LowPX_TIT-1990-56TIT-1990-56 reading frozen
15 Aug 2025MediumPX_LIT-455A-53AInstall cover plate for MCP cracking
08 Aug 2025MediumPX_TIT-1681BAR25/tranmsitter low performance
07 Aug 2025LowPX_TIT-680-43BInstall scaffolding at TIT-680-43B

Recent goods issues

Posting dateQtyOrderOrder type
27 Jul 20261201000017737Corrective
25 Jun 20261201000031485Corrective
23 Apr 20261201000030822Corrective
28 Nov 20251203000032713Turnaround
28 Nov 20255203000032713Turnaround
23 Nov 20251201000010115Corrective
07 May 20251201000014785Corrective