CONNECTOR,MALE,1/4IN ODT,1/2IN NPT,SS316

Material 4100040116 · CONNECTOR · Plant 1000

AReduceExcess
Material
4100040116
Category
CONNECTOR
Base unit
EA
MRP type
Stock Item
Criticality
A (7 of 15 FuncLocs A/B)
Supplier
BERKAH REFRAKTORI PRATAMA PT
Lead time
30 d · P80 44 d
Unit price
Rp 84,105

Recommendation

  • 1.Forecast 4.0 EA/year: 4.0 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~30 days; expected demand during lead time 0.3.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 8.
  • 4.Stock 10 exceeds the level to keep (8) by 2.
  • 5.Installed on 15 FuncLoc(s), 7 of them criticality A/B.
  • 6.ML early warning: 31% probability of demand in the next 90 days.
ML early warningLast turnaround used 3Single sourceSame description as 13 other material numbers
On hand / on order
10 / 0
no open PO
Today Min / Max
2 / 6
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
8
order qty 4
Service level
100.0%
stockout risk now 0%
Unit price
Rp 84,105
PO history
ML early warning: 31% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 56 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (3 units) excluded from the baseline.

Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 861.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 15 functional locations

7 with criticality A/B · 19 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FIT-1105
QUENCH WATER FLOW
A140.90
PX_PIT-1863B-26
PRESSURE
A100.04
PX_TEL-1280
CRACKED GAS OUTLET BF-112
A100.01
PX_TEL-421-46
TEMPERATURE
A200.01
PX_PIT-742A
DEMIN WATER PRESSURE
B100.04
PX_TEL-306A-49B
CRACKED GAS OUTLET BF-107
B400.01
PX_TEL-784
HE-1034A OUTLET
B100.01
PX_PGI-522D
BF-103 DISCHARGE
C120.44
PX_PGI-1702B-57
VD-157B SUCTION
C110.44
PX_LIT-1440-40
KC-660A LEVEL
C100.03
PX_PGI-348-24B
PP-1373A DISCHARGE
C100.02
PX_FIT-834A
CL-894 INLET FLOW
S100.04

Lead time and procurement

Lead time 30 ± 14 days (PO history, 6 PO lines) · on-time 43%

PR dateTypeQtyUnit priceDeliveryLead time
19 Jul 2026PR03
Regular replenishment
4Rp 83,60321 Aug 202633 d
11 May 2026PR06
Regular replenishment
5Rp 87,09524 Jun 202644 d
04 Dec 2025PR03
Regular replenishment
4Rp 84,60619 Jan 202646 d
06 Aug 2025PR03
Regular replenishment
2Rp 82,49723 Aug 202517 d
13 Jul 2025PR03
Regular replenishment
4Rp 83,03110 Aug 202528 d
20 May 2025PR03
Regular replenishment
4Rp 85,81302 Jun 202513 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Jun 2026MediumPX_FIT-1105FIT-1105 reading frozen
16 Apr 2026MediumPX_PGI-522DInspection PGI-522D.ok
02 Jan 2026EmergencyPX_FIT-1105Painting FIT-1105
15 Sept 2025LowPX_FIT-1105Leak from packing
05 Jul 2025MediumPX_PGI-1702B-57Replace PGI-1702B-57
23 May 2025MediumPX_FIT-1105Install cover plate for MCP cracking
21 May 2025LowPX_PGI-522DPGI-522D broken

Recent goods issues

Posting dateQtyOrderOrder type
06 Aug 20261201000005043Corrective
14 Jan 20261201000037385Corrective
29 Dec 20252201000025173Corrective
08 Dec 20251201000017361Corrective
03 Nov 20251203000039255Turnaround
02 Nov 20251203000039255Turnaround
01 Nov 20251203000039255Turnaround
23 Sept 20251201000035047Corrective
08 Jul 20252201000030225Corrective