CONNECTOR,MALE,1/4IN ODT,1/4IN NPT,SS316

Material 4100040201 · CONNECTOR · Plant 1000

AMaintainHealthy
Material
4100040201
Category
CONNECTOR
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
29 d · P80 43 d
Unit price
Rp 122,853 (est.)

Recommendation

  • 1.Forecast 2.0 EA/year: 2.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~29 days; expected demand during lead time 0.2.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 5.
  • 4.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Price estimatedLead time estimatedSame description as 16 other material numbers
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
5
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 122,853
Category + unit estimate
ML early warning: 20% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 79 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 590.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 4 functional locations

3 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TEL-810
PP-474A OUTLET
A100.01
PX_PIT-1131B-35B
COOLING WATER PRESSURE
B151.75
UT_TEL-526B
TEMPERATURE
B100.01
PX_TEL-1683
PP-682A OUTLET
C100.01

Lead time and procurement

Lead time 29 ± 16 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
08 Sept 2026MediumPX_PIT-1131B-35BPIT-1131B-35B error
20 Aug 2026MediumPX_PIT-1131B-35BPIT-1131B-35B error
09 Jun 2026MediumPX_PIT-1131B-35BPIT-1131B-35B reading frozen
08 May 2026MediumPX_PIT-1131B-35BCheck PIT-1131B-35B.ok
07 May 2025MediumPX_PIT-1131B-35BInstall scaffolding at PIT-1131B-35B

Recent goods issues

Posting dateQtyOrderOrder type
14 Jul 20261205000009079Other maintenance
10 Jun 20261201000000811Corrective
27 Jan 20261201000012307Corrective