CONNECTOR,MALE,1/4IN ODT,1/2IN NPT,SS316

Material 4100040242 · CONNECTOR · Plant 1000

ATransferCriticalStockout
Material
4100040242
Category
CONNECTOR
Base unit
EA
MRP type
Stock Item
Criticality
A (4 of 6 FuncLocs A/B)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
29 d · P80 38 d
Unit price
Rp 71,206

Recommendation

  • 1.Forecast 0.5 EA/year: 0.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~29 days; expected demand during lead time 0.0.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.On hand 0 + on order 1 is at or below the reorder point: 1 needed.
  • 5.Installed on 6 FuncLoc(s), 4 of them criticality A/B.
  • 6.Identical part 4100040931 holds spare stock: transfer 1 EA instead of buying — no purchase needed.
Single sourceOpen POSame description as 13 other material numbers
On hand / on order
0 / 1
next delivery 25 Oct 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.9%
stockout risk now 0%
Unit price
Rp 71,206
PO history
ML early warning: 23% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 35 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 151.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 6 functional locations

4 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TEL-1543
TEMPERATURE
A100.01
PY_LIT-1742A-50A
PP-448 LEVEL
A100.03
PX_FIT-1732A
HE-1774A INLET FLOW
B100.04
PX_TEL-652
TEMPERATURE
B100.01
PX_LIT-1681C-47B
LEVEL
C100.03
PX_LIT-385A-1
LEVEL
C100.03

Lead time and procurement

Lead time 29 ± 15 days (PO history, 3 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
17 Sept 2026PR03
Regular replenishment
1Rp 68,95025 Oct 2026
open
38 d
20 Aug 2026PR03
Regular replenishment
2Rp 71,20626 Sept 202637 d
04 Aug 2026PR06
Regular replenishment
1Rp 71,32215 Aug 202611 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
27 Aug 20261201000002052Corrective