Sparely
DU

CONNECTOR,MALE,1/2IN ODT,1/4IN NPT,SS316

Material 4100040797 · CONNECTOR · Plant 1000

ATransferNormalSlow-moving
Material
4100040797
Category
CONNECTOR
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 3 FuncLocs A/B)
Supplier
LANGIT MESINDO GLOBAL PT
Lead time
23 d · P80 22 d
Unit price
Rp 475,959

Recommendation

  • 1.Forecast 0.1 EA/year: 0.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~23 days; expected demand during lead time 0.0.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.On hand 1 + on order 0 is at or below the reorder point: 1 needed.
  • 5.Installed on 3 FuncLoc(s), 3 of them criticality A/B.
  • 6.Identical part 4100041587 holds spare stock: transfer 1 EA instead of buying — no purchase needed.
Single sourceSame description as 18 other material numbers
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
100.0%
stockout risk now 0%
Unit price
Rp 475,959
PO history
ML early warning: 28% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 374 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 41.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 3 functional locations

3 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TEL-471
TEMPERATURE
A200.01
PX_PGI-357-35A
KC-538 DISCHARGE
B100.02
PY_PGI-1527A
PRESSURE GAUGE
B100.02

Lead time and procurement

Lead time 23 ± 10 days (PO history, 5 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
30 Aug 2026PR03
Regular replenishment
2Rp 452,58111 Sept 202612 d
20 Aug 2026PR03
Regular replenishment
1Rp 476,05008 Sept 202619 d
22 Jul 2026PR03
Regular replenishment
1Rp 453,16322 Aug 202631 d
14 Dec 2025PR06
Regular replenishment
2Rp 480,47930 Dec 202516 d
04 Dec 2025PR03
Regular replenishment
1Rp 475,95924 Dec 202520 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
22 Sept 20251201000034151Corrective