TUBING,TYPE HS18,NBR
Material 4100041746 · TUBING · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100041746
- Category
- TUBING
- Base unit
- M
- MRP type
- Stock Item
- Criticality
- A (12 of 40 FuncLocs A/B)
- Supplier
- KARYA ENERGI SENTOSA PT
- Lead time
- 32 d · P80 36 d
- Unit price
- Rp 452,501
Recommendation
- 1.Forecast 228 M/year: 228 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~32 days; expected demand during lead time 20.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 152, order up to 239.
- 4.On hand 135 + on order 0 is at or below the reorder point: order 104 now.
- 5.Installed on 40 FuncLoc(s), 12 of them criticality A/B.
- 6.ML early warning: 69% probability of demand in the next 90 days.
Proposed purchase requisition
104 M
Rp 47.1M · order by 01 Oct 2026
Expected arrival ≈ 32 days
ML early warningSingle source
On hand / on order
135 / 0
no open PO
Today Min / Max
23 / 72
static parameters in BoM
Rec. Min (reorder point)
152
safety stock 133
Rec. Max
239
order qty 87
Service level
99.9%
stockout risk now 1%
Unit price
Rp 452,501
PO history
ML early warning: 69% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 83 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Lumpy · 8 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~21 days.
Installed on 40 functional locations
12 with criticality A/B · 300 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_TIT-556A TEMPERATURE | A | 25 | 1 | 0.47 |
| PX_FIT-1016-44B DILUTION STEAM FLOW | A | 10 | 0 | 0.04 |
| PX_FIT-181 CHARGE GAS FLOW | A | 0.32 | 0 | 0.04 |
| PX_TIT-446 HE-896C TEMPERATURE | A | 5 | 0 | 0.04 |
| PX_FIT-1693A FLOW | B | 1 | 1 | 0.04 |
| PX_FIT-1057 FLOW | B | 0.32 | 0 | 0.04 |
| PX_FIT-433A-16A FLOW | B | 5 | 0 | 0.04 |
| PX_LIT-1247 LEVEL | B | 10 | 0 | 0.03 |
| PX_PIT-1324 PRESSURE | B | 10 | 0 | 0.04 |
| PX_PIT-1531 HE-1967C PRESSURE | B | 0.32 | 0 | 0.04 |
| PX_PIT-1770 RICH AMINE PRESSURE | B | 1 | 0 | 0.04 |
| PX_PIT-1842A METHANOL PRESSURE | B | 2.5 | 0 | 0.04 |
Lead time and procurement
Lead time 32 ± 14 days (PO history, 5 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 11 May 2026 | PR06 Regular replenishment | 108 | Rp 436,115 | 27 May 2026 | 16 d |
| 09 Feb 2026 | PR06 Regular replenishment | 137 | Rp 438,325 | 30 Mar 2026 | 49 d |
| 23 Dec 2025 | PR03 Regular replenishment | 146 | Rp 452,501 | 13 Jan 2026 | 21 d |
| 23 Jun 2025 | PR03 Regular replenishment | 137 | Rp 471,068 | 19 Jul 2025 | 26 d |
| 24 May 2025 | PR03 Regular replenishment | 117 | Rp 462,710 | 26 Jun 2025 | 33 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | Medium | PX_PIT-758 | Install scaffolding at PIT-758 |
| 05 Sept 2026 | Medium | PX_FIT-1672-48A | FIT-1672-48A reading frozen |
| 29 Jul 2026 | High | PX_PIT-758 | PIT-758 error |
| 27 Jul 2026 | Medium | PX_FIT-1672-48A | Repair insulation FIT-1672-48A |
| 16 Jul 2026 | Medium | PX_PIT-794A | Install cover plate for MCP cracking |
| 20 May 2026 | Medium | PX_PIT-578A | AR25/tranmsitter low performance |
| 24 Feb 2026 | Medium | PX_PIT-578A | Install scaffolding at PIT-578A |
| 05 Nov 2025 | Low | PX_PIT-688-21A | PIT-688-21A error |
| 25 Sept 2025 | Medium | PX_PIT-758 | Check PIT-758.ok |
| 15 Aug 2025 | Medium | PX_TIT-556A | [MSI-B-25-FTU-227] Permanent repair |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 10 Jul 2026 | 20 | 201000004677 | Corrective |
| 15 Jun 2026 | 100 | 201000014984 | Corrective |
| 13 Jan 2026 | 10 | 201000002462 | Corrective |
| 16 Dec 2025 | 10 | 201000018349 | Corrective |
| 11 Dec 2025 | 5 | 201000005387 | Corrective |
| 11 Dec 2025 | 50 | 201000005387 | Corrective |
| 11 Dec 2025 | 5 | 201000011198 | Corrective |
| 06 Aug 2025 | 5 | 201000016556 | Corrective |
| 24 Jul 2025 | 100 | 201000014078 | Corrective |
| 22 Jul 2025 | 100 | 201000023257 | Corrective |