TUBING,TYPE VK365,MONEL

Material 4100043090 · TUBING · Plant 1000

CMonitorSlow-moving
Material
4100043090
Category
TUBING
Base unit
M
MRP type
Stock Item
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
SURYA ENERGI JAYA PT
Lead time
34 d · P80 49 d
Unit price
Rp 136,049

Recommendation

  • 1.Forecast 46 M/year: 46 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~34 days; expected demand during lead time 4.3.
  • 3.A 95.8% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 100.
Single source
On hand / on order
13 / 0
no open PO
Today Min / Max
15 / 43
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
100
order qty 100
Service level
95.8%
stockout risk now 4%
Unit price
Rp 136,049
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 493 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~21 days.

Installed on 1 functional locations

0 with criticality A/B · 2.5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_LIT-975B
PP-392A LEVEL
C2.541.32

Lead time and procurement

Lead time 34 ± 16 days (PO history + category, 2 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
17 Dec 2025PR03
Regular replenishment
47Rp 138,26921 Jan 202635 d
02 Sept 2025PR03
Regular replenishment
13Rp 133,82829 Sept 202527 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Oct 2025LowPX_LIT-975BAR25/tranmsitter low performance
29 Sept 2025LowPX_LIT-975BRepair insulation LIT-975B
28 Aug 2025LowPX_LIT-975BLIT-975B abnormal indication
15 May 2025LowPX_LIT-975BAR25/tranmsitter low performance

Recent goods issues

Posting dateQtyOrderOrder type
26 May 2025100201000028666Corrective