Sparely
DU

TRIM SET,CONTROL VALVE,MODEL LA610,CS

Material 4100043339 · TRIM SET · Plant 1000

ALong-leadReorderCriticalBelow reorder point
Material
4100043339
Category
TRIM SET
Base unit
SET
MRP type
Stock Item
Criticality
A (37 of 67 FuncLocs A/B)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
203 d · P80 295 d
Unit price
Rp 27.5M

Recommendation

  • 1.Forecast 21 SET/year: 19 unplanned (recency-weighted compound poisson (own history)) + 2.1 from the maintenance plan.
  • 2.Lead time ~203 days; expected demand during lead time 12 (incl. 1.4 planned).
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 32, order up to 36.
  • 4.On hand 2 + on order 17 is at or below the reorder point: order 17 now.
  • 5.Long lead time: 80% of deliveries took up to 295 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 67 FuncLoc(s), 37 of them criticality A/B.
  • 7.ML early warning: 95% probability of demand in the next 90 days.
Proposed purchase requisition
17 SET
Rp 467.5M · order by 01 Oct 2026
Expected arrival ≈ 203 days
Long-leadML early warningSingle sourceAbnormal consumptionOpen POPlanned demand in lead time
On hand / on order
2 / 17
next delivery 03 Feb 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
32
safety stock 21
Rec. Max
36
order qty 4
Service level
99.9%
stockout risk now 13%
Unit price
Rp 27.5M
PO history
ML early warning: 95% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 6 issue days in the last 180 days, last issue 6 days ago, 7 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 16 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 19.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 67 functional locations

37 with criticality A/B · 83 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-235B
VD-719 OUTLET FLOW
A130.96
PX_LCV-275C
HE-556A LEVEL CONTROL
A120.55
PX_PCV-1466B
BY PASS DUCT
A120.51
PX_FCV-1909
VD-1070A OUTLET FLOW
A110.54
PX_LCV-1581
LEVEL CONTROL VALVE
A110.12
PX_PCV-1274
PRESSURE CONTROL VALVE
A110.08
PX_TCV-310
PP-745 TEMP CONTROL
A110.12
PX_FCV-1081A
CONTROL VALVE
A100.11
PX_FCV-1181
CONTROL VALVE
A100.11
PX_FCV-1224
BY PASS LINE
A100.11
PX_FCV-1264A
CONTROL VALVE
A100.11
PX_FCV-837C
HYDROGEN FLOW CONTROL
A100.11

Lead time and procurement

Lead time 203 ± 81 days (PO history, 3 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
08 Apr 2026PR03
Regular replenishment
5Rp 28.2M28 Jul 2027
open
476 d
18 Dec 2025PR03
Regular replenishment
9Rp 28.0M14 Sept 2026270 d
18 Sept 2025PR06
Regular replenishment
12Rp 27.5M03 Feb 2027
open
503 d
15 Jul 2025PR06
Regular replenishment
11Rp 26.7M22 May 2026311 d
30 May 2025PR03
Regular replenishment
8Rp 26.6M06 Nov 2025160 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Dec 2026PX_PCV-1274Final Element Overhaul; Control Valve0.72
01 Apr 2027PX_PCV-1747Final Element Overhaul; CV0.72
01 Sept 2027PX_LCV-775Final Element Overhaul; Control Valve0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 Sept 2026MediumPX_PCV-357AOverhaul PCV-357A
11 Sept 2026LowPY_TCV-441AReplace lamp as per PM finding
04 Sept 2026LowPX_PCV-1466BPCV-1466B; valve hunting
02 Sept 2026LowPX_TCV-687Install scaffolding at TCV-687
19 Aug 2026MediumPX_FCV-235BFCV-235B; valve hunting
18 Aug 2026LowPX_LCV-275CLCV-275C passing
11 Aug 2026MediumPX_FCV-870[MSI-B-26-FHG-172/M] Replace line
29 Jul 2026MediumPX_LCV-1252LCV-1252 passing
02 Jul 2026LowPX_LCV-1252LCV-1252 stuck
30 Jun 2026MediumPX_FCV-919AFCV-919A; IA leak from regulator

Recent goods issues

Posting dateQtyOrderOrder type
25 Sept 20264201000013974Corrective
13 Sept 20262201000031329Corrective
31 Aug 20261201000001231Corrective
17 Jul 20262201000019779Corrective
25 Jun 20261201000033706Corrective
16 May 20263201000030117Corrective
01 Apr 20261201000031203Corrective
10 Feb 20261201000033056Corrective
28 Dec 20251201000028079Corrective
21 Dec 20251201000033420Corrective
17 Dec 20251201000035232Corrective
24 Nov 20251201000017774Corrective
12 Aug 20253205000008235Other maintenance
07 Jul 20252201000015275Corrective
06 Jul 20251201000015275Corrective