TRIM SET,CONTROL VALVE,MODEL LA610,CS
Material 4100043339 · TRIM SET · Plant 1000
ALong-leadReorderCriticalBelow reorder point
- Material
- 4100043339
- Category
- TRIM SET
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (37 of 67 FuncLocs A/B)
- Supplier
- KARYA ENERGI SENTOSA PT
- Lead time
- 203 d · P80 295 d
- Unit price
- Rp 27.5M
Recommendation
- 1.Forecast 21 SET/year: 19 unplanned (recency-weighted compound poisson (own history)) + 2.1 from the maintenance plan.
- 2.Lead time ~203 days; expected demand during lead time 12 (incl. 1.4 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 32, order up to 36.
- 4.On hand 2 + on order 17 is at or below the reorder point: order 17 now.
- 5.Long lead time: 80% of deliveries took up to 295 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 67 FuncLoc(s), 37 of them criticality A/B.
- 7.ML early warning: 95% probability of demand in the next 90 days.
Proposed purchase requisition
17 SET
Rp 467.5M · order by 01 Oct 2026
Expected arrival ≈ 203 days
Long-leadML early warningSingle sourceAbnormal consumptionOpen POPlanned demand in lead time
On hand / on order
2 / 17
next delivery 03 Feb 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
32
safety stock 21
Rec. Max
36
order qty 4
Service level
99.9%
stockout risk now 13%
Unit price
Rp 27.5M
PO history
ML early warning: 95% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 6 issue days in the last 180 days, last issue 6 days ago, 7 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 16 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 19.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.
Installed on 67 functional locations
37 with criticality A/B · 83 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-235B VD-719 OUTLET FLOW | A | 1 | 3 | 0.96 |
| PX_LCV-275C HE-556A LEVEL CONTROL | A | 1 | 2 | 0.55 |
| PX_PCV-1466B BY PASS DUCT | A | 1 | 2 | 0.51 |
| PX_FCV-1909 VD-1070A OUTLET FLOW | A | 1 | 1 | 0.54 |
| PX_LCV-1581 LEVEL CONTROL VALVE | A | 1 | 1 | 0.12 |
| PX_PCV-1274 PRESSURE CONTROL VALVE | A | 1 | 1 | 0.08 |
| PX_TCV-310 PP-745 TEMP CONTROL | A | 1 | 1 | 0.12 |
| PX_FCV-1081A CONTROL VALVE | A | 1 | 0 | 0.11 |
| PX_FCV-1181 CONTROL VALVE | A | 1 | 0 | 0.11 |
| PX_FCV-1224 BY PASS LINE | A | 1 | 0 | 0.11 |
| PX_FCV-1264A CONTROL VALVE | A | 1 | 0 | 0.11 |
| PX_FCV-837C HYDROGEN FLOW CONTROL | A | 1 | 0 | 0.11 |
Lead time and procurement
Lead time 203 ± 81 days (PO history, 3 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 08 Apr 2026 | PR03 Regular replenishment | 5 | Rp 28.2M | 28 Jul 2027 open | 476 d |
| 18 Dec 2025 | PR03 Regular replenishment | 9 | Rp 28.0M | 14 Sept 2026 | 270 d |
| 18 Sept 2025 | PR06 Regular replenishment | 12 | Rp 27.5M | 03 Feb 2027 open | 503 d |
| 15 Jul 2025 | PR06 Regular replenishment | 11 | Rp 26.7M | 22 May 2026 | 311 d |
| 30 May 2025 | PR03 Regular replenishment | 8 | Rp 26.6M | 06 Nov 2025 | 160 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Dec 2026 | PX_PCV-1274 | Final Element Overhaul; Control Valve | 0.72 |
| 01 Apr 2027 | PX_PCV-1747 | Final Element Overhaul; CV | 0.72 |
| 01 Sept 2027 | PX_LCV-775 | Final Element Overhaul; Control Valve | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 21 Sept 2026 | Medium | PX_PCV-357A | Overhaul PCV-357A |
| 11 Sept 2026 | Low | PY_TCV-441A | Replace lamp as per PM finding |
| 04 Sept 2026 | Low | PX_PCV-1466B | PCV-1466B; valve hunting |
| 02 Sept 2026 | Low | PX_TCV-687 | Install scaffolding at TCV-687 |
| 19 Aug 2026 | Medium | PX_FCV-235B | FCV-235B; valve hunting |
| 18 Aug 2026 | Low | PX_LCV-275C | LCV-275C passing |
| 11 Aug 2026 | Medium | PX_FCV-870 | [MSI-B-26-FHG-172/M] Replace line |
| 29 Jul 2026 | Medium | PX_LCV-1252 | LCV-1252 passing |
| 02 Jul 2026 | Low | PX_LCV-1252 | LCV-1252 stuck |
| 30 Jun 2026 | Medium | PX_FCV-919A | FCV-919A; IA leak from regulator |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 25 Sept 2026 | 4 | 201000013974 | Corrective |
| 13 Sept 2026 | 2 | 201000031329 | Corrective |
| 31 Aug 2026 | 1 | 201000001231 | Corrective |
| 17 Jul 2026 | 2 | 201000019779 | Corrective |
| 25 Jun 2026 | 1 | 201000033706 | Corrective |
| 16 May 2026 | 3 | 201000030117 | Corrective |
| 01 Apr 2026 | 1 | 201000031203 | Corrective |
| 10 Feb 2026 | 1 | 201000033056 | Corrective |
| 28 Dec 2025 | 1 | 201000028079 | Corrective |
| 21 Dec 2025 | 1 | 201000033420 | Corrective |
| 17 Dec 2025 | 1 | 201000035232 | Corrective |
| 24 Nov 2025 | 1 | 201000017774 | Corrective |
| 12 Aug 2025 | 3 | 205000008235 | Other maintenance |
| 07 Jul 2025 | 2 | 201000015275 | Corrective |
| 06 Jul 2025 | 1 | 201000015275 | Corrective |