TRIM SET,CONTROL VALVE,SIZE NN15,PTFE

Material 4100043368 · TRIM SET · Plant 1000

ALong-leadMaintainHealthy
Material
4100043368
Category
TRIM SET
Base unit
SET
MRP type
Stock Item
Criticality
A (9 of 15 FuncLocs A/B)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
192 d · P80 263 d
Unit price
Rp 289.9M

Recommendation

  • 1.Forecast 2.2 SET/year: 2.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~192 days; expected demand during lead time 1.2.
  • 3.A 99.3% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 5.
  • 4.Long lead time: 80% of deliveries took up to 263 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 15 FuncLoc(s), 9 of them criticality A/B.
  • 6.ML early warning: 35% probability of demand in the next 90 days.
Long-leadML early warningSingle sourceOpen PO
On hand / on order
2 / 3
next delivery 28 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 3
Rec. Max
5
order qty 1
Service level
99.3%
stockout risk now 0%
Unit price
Rp 289.9M
PO history
ML early warning: 35% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 179 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 15 functional locations

9 with criticality A/B · 18 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1156C
PP-1323A OUTLET FLOW
A100.11
PX_FCV-1679A
CONTROL VALVE
A100.11
PX_TCV-946
TEMPERATURE CONTROL VALVE
A100.12
PX_FCV-1003A
BY PASS LINE
B100.11
PX_FCV-1761
FLUSHING OIL FLOW CONTROL
B100.11
PX_LCV-1697
LEVEL CONTROL VALVE
B100.12
PX_PCV-499
BY PASS DUCT
B100.08
PX_PCV-913
BY PASS DUCT
B100.08
PY_FCV-1766
WASH WATER FLOW CONTROL
B100.11
PX_PCV-372
PRESSURE CONTROL VALVE
C130.94
PX_FCV-327
CONTROL VALVE
C110.54
PX_FCV-1089
CONTROL VALVE
C100.11

Lead time and procurement

Lead time 192 ± 71 days (PO history, 5 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
11 Aug 2026PR03
Regular replenishment
1Rp 283.6M08 Dec 2026
open
119 d
06 Aug 2026PR03
Regular replenishment
1Rp 293.6M21 Feb 2027
open
199 d
16 Feb 2026PR03
Regular replenishment
1Rp 295.6M28 Nov 2026
open
285 d
08 Oct 2025PR03
Regular replenishment
2Rp 278.0M23 Jun 2026258 d
08 Aug 2025PR06
Regular replenishment
1Rp 289.9M20 Feb 2026196 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 May 2026LowPX_PCV-372PCV-372 passing
08 Feb 2026LowPX_PCV-372PCV-372; valve hunting
20 Jun 2025LowPX_FCV-327FCV-327 stuck
15 May 2025MediumPX_PCV-372PSM25/Overhaul PCV-372

Recent goods issues

Posting dateQtyOrderOrder type
05 Apr 20261205000023443Other maintenance
23 Feb 20261201000001108Corrective
13 Feb 20261201000018387Corrective
27 Nov 20251201000004723Corrective