TRIM SET,CONTROL VALVE,MODEL HW157,PTFE
Material 4100043409 · TRIM SET · Plant 1000
AReorderCriticalStockout
- Material
- 4100043409
- Category
- TRIM SET
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (5 of 11 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 159 d · P80 236 d
- Unit price
- Rp 78.5M (est.)
Recommendation
- 1.Forecast 2.5 SET/year: 2.5 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~159 days; expected demand during lead time 1.1.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 6.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 6 now.
- 5.Installed on 11 FuncLoc(s), 5 of them criticality A/B.
Proposed purchase requisition
6 SET
Rp 471.0M · order by 01 Oct 2026
Expected arrival ≈ 159 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 4
Rec. Max
6
order qty 1
Service level
99.9%
stockout risk now 67%
Unit price
Rp 78.5M
Category + unit estimate
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 89 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.
Installed on 11 functional locations
5 with criticality A/B · 14 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-907A BY PASS LINE | A | 1 | 0 | 0.11 |
| PX_LCV-571 LEVEL CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_TCV-1626 VD-272 TEMP CONTROL | A | 3 | 0 | 0.12 |
| PY_FCV-178 PP-339C OUTLET FLOW | A | 1 | 0 | 0.11 |
| PX_TCV-1022 TEMPERATURE CONTROL VALVE | B | 1 | 2 | 0.55 |
| PX_TCV-771 TEMPERATURE CONTROL VALVE | C | 1 | 3 | 0.98 |
| PY_LCV-1952 VD-125 LEVEL CONTROL | C | 1 | 2 | 0.97 |
| PX_FCV-456A BY PASS LINE | C | 1 | 0 | 0.11 |
| PX_TCV-135B TEMPERATURE CONTROL VALVE | C | 1 | 0 | 0.12 |
| PX_LCV-1691A LEVEL CONTROL VALVE | S | 1 | 9 | 3.97 |
| PX_LCV-915 PP-273A LEVEL CONTROL | S | 2 | 2 | 0.55 |
Lead time and procurement
Lead time 159 ± 83 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 13 Sept 2026 | High | PX_LCV-1691A | [MSI-B-26-KJJ-391/M] Replace line |
| 13 Sept 2026 | High | PX_TCV-771 | TCV-771 passing |
| 17 Aug 2026 | Medium | PX_LCV-915 | Overhaul LCV-915 |
| 22 Jul 2026 | Medium | PX_LCV-1691A | LCV-1691A; small leak at packing |
| 02 Apr 2026 | Low | PX_LCV-1691A | LCV-1691A; valve hunting |
| 11 Mar 2026 | Low | PX_LCV-1691A | Replace lamp as per PM finding |
| 07 Mar 2026 | Low | PX_LCV-1691A | Install cover plate for MCP cracking |
| 27 Feb 2026 | Low | PX_LCV-1691A | Leak from packing |
| 02 Jan 2026 | Medium | PX_LCV-1691A | LCV-1691A; IA leak from regulator |
| 30 Dec 2025 | Medium | PX_LCV-1691A | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 04 Jul 2026 | 1 | 201000013426 | Corrective |
| 29 Jan 2026 | 1 | 201000017678 | Corrective |