TRIM SET,CONTROL VALVE,SIZE QH233,GRAPHI

Material 4100043468 · TRIM SET · Plant 1000

BLong-leadReduceSlow-moving
Material
4100043468
Category
TRIM SET
Base unit
SET
MRP type
Stock Item
Criticality
B (3 of 3 FuncLocs A/B)
Supplier
MEGA TEKNIK MAKMUR PT
Lead time
147 d · P80 198 d
Unit price
Rp 55.2M

Recommendation

  • 1.Forecast 0.6 SET/year: 0.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~147 days; expected demand during lead time 0.2.
  • 3.A 89.5% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 2.
  • 4.Stock 5 exceeds the level to keep (2) by 3.
  • 5.Long lead time: 80% of deliveries took up to 198 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 3 FuncLoc(s), 3 of them criticality A/B.
Long-leadSingle source
On hand / on order
5 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
2
order qty 2
Service level
89.5%
stockout risk now 0%
Unit price
Rp 55.2M
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 280 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 109.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~75 days.

Installed on 3 functional locations

3 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_LCV-158
PP-1143B LEVEL CONTROL
B100.12
PX_PCV-1406D
BY PASS DUCT
B100.08
PX_TCV-700
TEMPERATURE CONTROL VALVE
B100.12

Lead time and procurement

Lead time 147 ± 79 days (PO history, 4 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
02 Jul 2026PR03
Regular replenishment
2Rp 53.0M16 Sept 202676 d
06 Jan 2026PR06
Regular replenishment
2Rp 56.5M07 Jul 2026182 d
24 Oct 2025PR03
Regular replenishment
1Rp 55.9M03 Jun 2026222 d
10 Jul 2025PR03
Regular replenishment
2Rp 54.5M22 Sept 202574 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
25 Dec 20252201000038136Corrective