TRIM SET,CONTROL VALVE,TYPE DM761,PTFE

Material 4100043475 · TRIM SET · Plant 1000

AReduceNon-moving
Material
4100043475
Category
TRIM SET
Base unit
SET
MRP type
Stock Item
Criticality
A (4 of 7 FuncLocs A/B)
Supplier
No PO history
Lead time
159 d · P80 236 d
Unit price
Rp 78.5M (est.)

Recommendation

  • 1.Forecast 0.0 SET/year: 0.0 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~159 days; expected demand during lead time 0.0.
  • 3.A 98.0% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.Stock 18 exceeds the level to keep (1) by 17.
  • 5.Installed on 7 FuncLoc(s), 4 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
18 / 0
no open PO
Today Min / Max
5 / 12
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
98.0%
stockout risk now 0%
Unit price
Rp 78.5M
Category + unit estimate
ML early warning: 13% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 73.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 7 functional locations

4 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TCV-749
PP-136B TEMP CONTROL
A110.55
PX_PCV-343
HE-1326D PRESSURE CONTROL
A100.08
PX_PCV-650
BY PASS DUCT
A100.08
PX_FCV-1569B
CONTROL VALVE
B100.11
PX_TCV-1851
PP-1056 TEMP CONTROL
C120.12
PX_LCV-492
HE-337B LEVEL CONTROL
C100.12
PX_PCV-429
BY PASS DUCT
C100.08

Lead time and procurement

Lead time 159 ± 83 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
17 Sept 2026MediumPX_TCV-1851Install scaffolding at TCV-1851
12 Jun 2025MediumPX_TCV-749Install cover plate for MCP cracking
09 May 2025HighPX_TCV-1851TCV-1851 stuck

Recent goods issues

Never issued in the 17-month history.