TRIM SET,CONTROL VALVE,MODEL FY873,VITON

Material 4100043528 · TRIM SET · Plant 1000

BLong-leadMonitorSlow-moving
Material
4100043528
Category
TRIM SET
Base unit
SET
MRP type
Stock Item
Criticality
B (3 of 5 FuncLocs A/B)
Supplier
BUANA INDUSTRI LESTARI PT
Lead time
144 d · P80 236 d
Unit price
Rp 137.3M

Recommendation

  • 1.Forecast 1.6 SET/year: 0.8 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~144 days; expected demand during lead time 1.0 (incl. 0.7 planned).
  • 3.A 84.7% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 3.
  • 4.Long lead time: 80% of deliveries took up to 236 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Long-leadSingle sourceOpen POPlanned demand in lead time
On hand / on order
3 / 2
next delivery 20 Jan 2027
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 0
Rec. Max
3
order qty 2
Service level
84.7%
stockout risk now 0%
Unit price
Rp 137.3M
PO history
ML early warning: 15% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 331 days ago, 0 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 168.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~75 days.

Installed on 5 functional locations

3 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_LCV-413
HE-1635C LEVEL CONTROL
B100.12
PX_PCV-1015
HE-1921D PRESSURE CONTROL
B100.08
PX_PCV-204
PP-588 PRESSURE CONTROL
B100.08
PX_TCV-734A
TEMPERATURE CONTROL VALVE
C100.12
PX_TCV-1082A
HE-171A TEMP CONTROL
S110.55

Lead time and procurement

Lead time 144 ± 83 days (PO history + category, 2 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
22 Sept 2026PR03
Regular replenishment
2Rp 138.4M20 Jan 2027
open
120 d
25 Jun 2025PR03
Regular replenishment
1Rp 136.2M26 Oct 2025123 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Dec 2026PX_TCV-1082AFinal Element Overhaul; Control Valve0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Jul 2025MediumPX_TCV-1082ALeak from packing

Recent goods issues

Posting dateQtyOrderOrder type
04 Nov 20252201000031022Corrective