TRIM SET,CONTROL VALVE,SIZE VM924,NBR

Material 4100043551 · TRIM SET · Plant 1000

AReorderNormalSlow-moving
Material
4100043551
Category
TRIM SET
Base unit
SET
MRP type
Non Stock
Criticality
A (9 of 10 FuncLocs A/B)
Supplier
No PO history
Lead time
159 d · P80 236 d
Unit price
Rp 78.5M (est.)

Recommendation

  • 1.Forecast 1.6 SET/year: 0.9 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~159 days; expected demand during lead time 1.1 (incl. 0.7 planned).
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 5.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 3 now.
  • 5.Installed on 10 FuncLoc(s), 9 of them criticality A/B.
Proposed purchase requisition
3 SET
Rp 235.5M · order by 01 Oct 2026
Expected arrival ≈ 159 days
Convert to Stock ItemPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 3
Rec. Max
5
order qty 1
Service level
99.9%
stockout risk now 6%
Unit price
Rp 78.5M
Category + unit estimate
ML early warning: 28% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 297 days ago, 0 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 10 functional locations

9 with criticality A/B · 13 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_LCV-897
HE-1660A LEVEL CONTROL
A131.40
PX_FCV-1295
CL-1039 OUTLET FLOW
A100.11
PX_LCV-1143A
LEVEL CONTROL VALVE
A400.12
PY_LCV-1648B
PP-120B LEVEL CONTROL
A100.12
PX_FCV-1861
CONTROL VALVE
B100.11
PX_LCV-1246
HE-554 LEVEL CONTROL
B100.12
PX_TCV-254
TEMPERATURE CONTROL VALVE
B100.12
PX_TCV-377
HE-1318B TEMP CONTROL
B100.12
PY_LCV-916
VD-1908 LEVEL CONTROL
B100.12
PY_TCV-162
PP-135A TEMP CONTROL
C100.12

Lead time and procurement

Lead time 159 ± 83 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Dec 2026PX_LCV-1246Final Element Overhaul; Control Valve0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
09 May 2026MediumPY_LCV-897Overhaul LCV-897
30 Aug 2025MediumPY_LCV-897LCV-897; IA leak from regulator
15 Jun 2025MediumPY_LCV-897LCV-897; IA leak from regulator

Recent goods issues

Posting dateQtyOrderOrder type
08 Dec 20251201000037522Corrective