TRIM SET,CONTROL VALVE,SIZE RF534,CS
Material 4100043624 · TRIM SET · Plant 1000
ALong-leadMaintainStockout
- Material
- 4100043624
- Category
- TRIM SET
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (1 of 4 FuncLocs A/B)
- Supplier
- SINAR SEJAHTERA LESTARI PT
- Lead time
- 183 d · P80 256 d
- Unit price
- Rp 42.5M
Recommendation
- 1.Forecast 3.6 SET/year: 3.6 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~183 days; expected demand during lead time 1.8.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 10.
- 4.Long lead time: 80% of deliveries took up to 256 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
- 6.ML early warning: 50% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemLast turnaround used 9Single sourceOpen PO
On hand / on order
0 / 12
next delivery 12 Feb 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 7
Rec. Max
10
order qty 2
Service level
99.8%
stockout risk now 0%
Unit price
Rp 42.5M
PO history
ML early warning: 50% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 40 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (9 units) excluded from the baseline.
Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.
Installed on 4 functional locations
1 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PCV-1496A PP-821 PRESSURE CONTROL | A | 1 | 0 | 0.08 |
| PX_FCV-381 C3 RECYCLE FLOW CONTROL | C | 1 | 2 | 0.54 |
| PX_TCV-1659A VD-756B TEMP CONTROL | S | 2 | 1 | 0.12 |
| PY_LCV-1630 LEVEL CONTROL VALVE | S | 1 | 0 | 0.12 |
Lead time and procurement
Lead time 183 ± 70 days (PO history, 5 PO lines) · on-time 33%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 13 Sept 2026 | PR06 Regular replenishment | 2 | Rp 41.2M | 12 Feb 2027 open | 152 d |
| 05 Sept 2026 | PR06 Regular replenishment | 3 | Rp 42.9M | 21 Feb 2027 open | 169 d |
| 01 Jun 2026 | PR01 Import / long-lead | 7 | Rp 42.6M | 06 Jun 2027 open | 370 d |
| 21 Feb 2026 | PR06 Regular replenishment | 5 | Rp 41.8M | 10 Jul 2026 | 139 d |
| 21 Jan 2026 | PR03 Regular replenishment | 6 | Rp 42.4M | 29 Sept 2026 | 251 d |
| 05 Dec 2025 | PR06 Regular replenishment | 3 | Rp 42.7M | 07 Sept 2026 | 276 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 18 Mar 2026 | Medium | PX_FCV-381 | FCV-381; IA leak from regulator |
| 26 May 2025 | High | PX_FCV-381 | FCV-381; valve hunting |
| 12 May 2025 | Medium | PX_TCV-1659A | PSM25/TCV-1659A; IA leak from regulator |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 22 Aug 2026 | 1 | 201000025267 | Corrective |
| 10 May 2026 | 2 | 201000021384 | Corrective |
| 21 Mar 2026 | 2 | 201000018631 | Corrective |
| 29 Dec 2025 | 1 | 203000016277 | Turnaround |
| 27 Dec 2025 | 2 | 203000016277 | Turnaround |
| 26 Dec 2025 | 5 | 203000016277 | Turnaround |
| 25 Dec 2025 | 1 | 203000016277 | Turnaround |
| 27 Jul 2025 | 1 | 201000029079 | Corrective |