TRIM SET,CONTROL VALVE,SIZE RF534,CS

Material 4100043624 · TRIM SET · Plant 1000

ALong-leadMaintainStockout
Material
4100043624
Category
TRIM SET
Base unit
SET
MRP type
Non Stock
Criticality
A (1 of 4 FuncLocs A/B)
Supplier
SINAR SEJAHTERA LESTARI PT
Lead time
183 d · P80 256 d
Unit price
Rp 42.5M

Recommendation

  • 1.Forecast 3.6 SET/year: 3.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~183 days; expected demand during lead time 1.8.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 10.
  • 4.Long lead time: 80% of deliveries took up to 256 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
  • 6.ML early warning: 50% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemLast turnaround used 9Single sourceOpen PO
On hand / on order
0 / 12
next delivery 12 Feb 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 7
Rec. Max
10
order qty 2
Service level
99.8%
stockout risk now 0%
Unit price
Rp 42.5M
PO history
ML early warning: 50% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 40 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (9 units) excluded from the baseline.

Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 4 functional locations

1 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PCV-1496A
PP-821 PRESSURE CONTROL
A100.08
PX_FCV-381
C3 RECYCLE FLOW CONTROL
C120.54
PX_TCV-1659A
VD-756B TEMP CONTROL
S210.12
PY_LCV-1630
LEVEL CONTROL VALVE
S100.12

Lead time and procurement

Lead time 183 ± 70 days (PO history, 5 PO lines) · on-time 33%

PR dateTypeQtyUnit priceDeliveryLead time
13 Sept 2026PR06
Regular replenishment
2Rp 41.2M12 Feb 2027
open
152 d
05 Sept 2026PR06
Regular replenishment
3Rp 42.9M21 Feb 2027
open
169 d
01 Jun 2026PR01
Import / long-lead
7Rp 42.6M06 Jun 2027
open
370 d
21 Feb 2026PR06
Regular replenishment
5Rp 41.8M10 Jul 2026139 d
21 Jan 2026PR03
Regular replenishment
6Rp 42.4M29 Sept 2026251 d
05 Dec 2025PR06
Regular replenishment
3Rp 42.7M07 Sept 2026276 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Mar 2026MediumPX_FCV-381FCV-381; IA leak from regulator
26 May 2025HighPX_FCV-381FCV-381; valve hunting
12 May 2025MediumPX_TCV-1659APSM25/TCV-1659A; IA leak from regulator

Recent goods issues

Posting dateQtyOrderOrder type
22 Aug 20261201000025267Corrective
10 May 20262201000021384Corrective
21 Mar 20262201000018631Corrective
29 Dec 20251203000016277Turnaround
27 Dec 20252203000016277Turnaround
26 Dec 20255203000016277Turnaround
25 Dec 20251203000016277Turnaround
27 Jul 20251201000029079Corrective