TRIM SET,CONTROL VALVE,TYPE NL545,CS
Material 4100043675 · TRIM SET · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100043675
- Category
- TRIM SET
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (3 of 7 FuncLocs A/B)
- Supplier
- PRIMA INDUSTRI SENTOSA PT
- Lead time
- 149 d · P80 236 d
- Unit price
- Rp 80.5M
Recommendation
- 1.Forecast 0.7 SET/year: 0.7 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~149 days; expected demand during lead time 0.3.
- 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 3 now.
- 5.Long lead time: 80% of deliveries took up to 236 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 7 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
3 SET
Rp 241.6M · order by 01 Oct 2026
Expected arrival ≈ 149 days
Long-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.7%
stockout risk now 25%
Unit price
Rp 80.5M
PO history
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 274 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.
Installed on 7 functional locations
3 with criticality A/B · 10 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-1324 BY PASS LINE | A | 1 | 0 | 0.11 |
| PX_PCV-1988 PP-1011D PRESSURE CONTROL | A | 1 | 0 | 0.08 |
| PX_TCV-529 TEMPERATURE CONTROL VALVE | B | 4 | 0 | 0.12 |
| PX_TCV-639 HE-1500B TEMP CONTROL | C | 1 | 2 | 0.55 |
| PX_LCV-492 HE-337B LEVEL CONTROL | C | 1 | 0 | 0.12 |
| PX_TCV-727D HE-1305 TEMP CONTROL | C | 1 | 0 | 0.12 |
| PX_FCV-273 CONTROL VALVE | S | 1 | 0 | 0.11 |
Lead time and procurement
Lead time 149 ± 83 days (PO history + category, 1 PO lines) · on-time 44%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 14 Jun 2025 | PR03 Regular replenishment | 1 | Rp 80.5M | 11 Oct 2025 | 119 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 07 Dec 2025 | Medium | PX_TCV-639 | TCV-639; small leak at packing |
| 07 May 2025 | Medium | PX_TCV-639 | TCV-639; small leak at packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 31 Dec 2025 | 1 | 204000003453 | Preventive |
| 17 Aug 2025 | 1 | 201000013787 | Corrective |