Sparely
DU

TRIM SET,CONTROL VALVE,SIZE FX406,CS

Material 4100043754 · TRIM SET · Plant 1000

CMaintainNo stock needed
Material
4100043754
Category
TRIM SET
Base unit
SET
MRP type
Stock Item
Criticality
C (0 of 2 FuncLocs A/B)
Supplier
PERMATA INSTRUMEN INTERNASIONAL PT
Lead time
160 d · P80 183 d
Unit price
Rp 181.4M

Recommendation

  • 1.Forecast 0.4 SET/year: 0.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~160 days; expected demand during lead time 0.2.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Convert to Non StockSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 15%
Unit price
Rp 181.4M
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 146 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 11.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~75 days.

Installed on 2 functional locations

0 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TCV-1012A
TEMPERATURE CONTROL VALVE
C110.12
PX_FCV-876
QUENCH WATER FLOW CONTROL
C100.11

Lead time and procurement

Lead time 160 ± 58 days (PO history, 4 PO lines) · on-time 47%

PR dateTypeQtyUnit priceDeliveryLead time
18 Apr 2026PR03
Regular replenishment
2Rp 177.6M29 Aug 2026133 d
02 Apr 2026PR06
Regular replenishment
2Rp 189.2M09 Sept 2026160 d
08 Aug 2025PR03
Regular replenishment
2Rp 182.5M13 Mar 2026217 d
01 Jul 2025PR06
Regular replenishment
2Rp 180.3M11 Nov 2025133 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 May 2025HighPX_TCV-1012ATCV-1012A passing

Recent goods issues

Posting dateQtyOrderOrder type
08 May 20261201000019580Corrective